Construction delays: a case study in the Brazilian Amazon

Detalhes bibliográficos
Autor(a) principal: Maués,Luiz Mauricio Furtado
Data de Publicação: 2017
Outros Autores: Santana,Wylliam Bessa, Santos,Paulo Cerqueira dos, Neves,Renato Martins das, Duarte,André Augusto Azevedo Montenegro
Tipo de documento: Artigo
Idioma: eng
Título da fonte: Ambiente construído (Online)
Texto Completo: http://old.scielo.br/scielo.php?script=sci_arttext&pid=S1678-86212017000300167
Resumo: Abstract he construction industry is one of the industrial sectors with the lowest rates of fulfilment of contract deadlines, especially in developing countries. This fact has been the focus of considerable discussions seeking to identify the causes of the delays. The main purpose of this paper is to use factor analysis to identify the factors that are correlated with delay, contemplating exclusively residential real estate projects and using a city in the Brazilian Amazon as a case study. Based on the database from the government agency that authorises constructions in the city of Belém (City Planning Department - Secretaria Municipal de Urbanismo, SEURB) and data from construction companies, the study investigated 274 construction projects from the past 11 years. Factor analysis and work with the variables that can be identified and measured in the initial phase of the project, i.e., during the feasibility study, demonstrate that the physical characteristics of the apartments and the construction project are the primary causes for variations in construction delays; these causes have not yet been reported in the literature. We hope that the results of this study will contribute to more consistent forecasting of construction time, minimising the risk of delays.
id ANTAC-1_37c2beca3389eb8bb1e86284e7b39888
oai_identifier_str oai:scielo:S1678-86212017000300167
network_acronym_str ANTAC-1
network_name_str Ambiente construído (Online)
repository_id_str
spelling Construction delays: a case study in the Brazilian AmazonRiskConstruction delaysFactor analysisAbstract he construction industry is one of the industrial sectors with the lowest rates of fulfilment of contract deadlines, especially in developing countries. This fact has been the focus of considerable discussions seeking to identify the causes of the delays. The main purpose of this paper is to use factor analysis to identify the factors that are correlated with delay, contemplating exclusively residential real estate projects and using a city in the Brazilian Amazon as a case study. Based on the database from the government agency that authorises constructions in the city of Belém (City Planning Department - Secretaria Municipal de Urbanismo, SEURB) and data from construction companies, the study investigated 274 construction projects from the past 11 years. Factor analysis and work with the variables that can be identified and measured in the initial phase of the project, i.e., during the feasibility study, demonstrate that the physical characteristics of the apartments and the construction project are the primary causes for variations in construction delays; these causes have not yet been reported in the literature. We hope that the results of this study will contribute to more consistent forecasting of construction time, minimising the risk of delays.Associação Nacional de Tecnologia do Ambiente Construído - ANTAC2017-07-01info:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersiontext/htmlhttp://old.scielo.br/scielo.php?script=sci_arttext&pid=S1678-86212017000300167Ambiente Construído v.17 n.3 2017reponame:Ambiente construído (Online)instname:Associação Nacional de Tecnologia do Ambiente Construído (ANTAC)instacron:ANTAC10.1590/s1678-86212017000300169info:eu-repo/semantics/openAccessMaués,Luiz Mauricio FurtadoSantana,Wylliam BessaSantos,Paulo Cerqueira dosNeves,Renato Martins dasDuarte,André Augusto Azevedo Montenegroeng2017-06-23T00:00:00Zoai:scielo:S1678-86212017000300167Revistahttps://seer.ufrgs.br/ambienteconstruidohttps://old.scielo.br/oai/scielo-oai.php||ambienteconstruido@ufrgs.br1678-86211415-8876opendoar:2017-06-23T00:00Ambiente construído (Online) - Associação Nacional de Tecnologia do Ambiente Construído (ANTAC)false
dc.title.none.fl_str_mv Construction delays: a case study in the Brazilian Amazon
title Construction delays: a case study in the Brazilian Amazon
spellingShingle Construction delays: a case study in the Brazilian Amazon
Maués,Luiz Mauricio Furtado
Risk
Construction delays
Factor analysis
title_short Construction delays: a case study in the Brazilian Amazon
title_full Construction delays: a case study in the Brazilian Amazon
title_fullStr Construction delays: a case study in the Brazilian Amazon
title_full_unstemmed Construction delays: a case study in the Brazilian Amazon
title_sort Construction delays: a case study in the Brazilian Amazon
author Maués,Luiz Mauricio Furtado
author_facet Maués,Luiz Mauricio Furtado
Santana,Wylliam Bessa
Santos,Paulo Cerqueira dos
Neves,Renato Martins das
Duarte,André Augusto Azevedo Montenegro
author_role author
author2 Santana,Wylliam Bessa
Santos,Paulo Cerqueira dos
Neves,Renato Martins das
Duarte,André Augusto Azevedo Montenegro
author2_role author
author
author
author
dc.contributor.author.fl_str_mv Maués,Luiz Mauricio Furtado
Santana,Wylliam Bessa
Santos,Paulo Cerqueira dos
Neves,Renato Martins das
Duarte,André Augusto Azevedo Montenegro
dc.subject.por.fl_str_mv Risk
Construction delays
Factor analysis
topic Risk
Construction delays
Factor analysis
description Abstract he construction industry is one of the industrial sectors with the lowest rates of fulfilment of contract deadlines, especially in developing countries. This fact has been the focus of considerable discussions seeking to identify the causes of the delays. The main purpose of this paper is to use factor analysis to identify the factors that are correlated with delay, contemplating exclusively residential real estate projects and using a city in the Brazilian Amazon as a case study. Based on the database from the government agency that authorises constructions in the city of Belém (City Planning Department - Secretaria Municipal de Urbanismo, SEURB) and data from construction companies, the study investigated 274 construction projects from the past 11 years. Factor analysis and work with the variables that can be identified and measured in the initial phase of the project, i.e., during the feasibility study, demonstrate that the physical characteristics of the apartments and the construction project are the primary causes for variations in construction delays; these causes have not yet been reported in the literature. We hope that the results of this study will contribute to more consistent forecasting of construction time, minimising the risk of delays.
publishDate 2017
dc.date.none.fl_str_mv 2017-07-01
dc.type.driver.fl_str_mv info:eu-repo/semantics/article
dc.type.status.fl_str_mv info:eu-repo/semantics/publishedVersion
format article
status_str publishedVersion
dc.identifier.uri.fl_str_mv http://old.scielo.br/scielo.php?script=sci_arttext&pid=S1678-86212017000300167
url http://old.scielo.br/scielo.php?script=sci_arttext&pid=S1678-86212017000300167
dc.language.iso.fl_str_mv eng
language eng
dc.relation.none.fl_str_mv 10.1590/s1678-86212017000300169
dc.rights.driver.fl_str_mv info:eu-repo/semantics/openAccess
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv text/html
dc.publisher.none.fl_str_mv Associação Nacional de Tecnologia do Ambiente Construído - ANTAC
publisher.none.fl_str_mv Associação Nacional de Tecnologia do Ambiente Construído - ANTAC
dc.source.none.fl_str_mv Ambiente Construído v.17 n.3 2017
reponame:Ambiente construído (Online)
instname:Associação Nacional de Tecnologia do Ambiente Construído (ANTAC)
instacron:ANTAC
instname_str Associação Nacional de Tecnologia do Ambiente Construído (ANTAC)
instacron_str ANTAC
institution ANTAC
reponame_str Ambiente construído (Online)
collection Ambiente construído (Online)
repository.name.fl_str_mv Ambiente construído (Online) - Associação Nacional de Tecnologia do Ambiente Construído (ANTAC)
repository.mail.fl_str_mv ||ambienteconstruido@ufrgs.br
_version_ 1754209103588098048