Multi-stage dumping sequence - a feasible waste management alternative for open pit mining

Detalhes bibliográficos
Autor(a) principal: Kuckartz,Bruno Tomasi
Data de Publicação: 2021
Outros Autores: Peroni,Rodrigo de Lemos, Rodrigues,Áttila Leães
Tipo de documento: Artigo
Idioma: eng
Título da fonte: REM - International Engineering Journal
Texto Completo: http://old.scielo.br/scielo.php?script=sci_arttext&pid=S2448-167X2021000200253
Resumo: Abstract Waste management and environmental aspects are progressively gathering attention in the mining industry. Mine planners must deal with increasingly complex tasks to balance between ore block schedules, waste disposal, operational cost and environmental reclamation. The mine incomes are generally related to mining and processing of the ore, thus most optimization researches regarding strategic mining usually focus mainly on ore extraction. Nevertheless, waste sequencing and disposal play an important role given that, in several situations in open pit mining, waste volumes are generally larger than ore volumes and must be moved to reach the buried and deeper ore bodies. In some cases, a significant percentage of operational costs is represented by waste haulage and disposal. Thus a careful planning strategy must be considered to minimize unnecessary expenses. Selecting locations for waste dumps is also a challenge. Many operational and technical aspects must be considered, not to mention the increasingly limiting environmental constraints. This definition can be very time consuming, and if it is not properly studied, may negatively impact the mine operation during its lifetime. This article investigates a new approach for mine waste management called the multi-stage dumping sequence (MSDS), suggesting the use of temporary waste dumps along the way to the final dump destination. Although this method requires material re-handling, which is considered a paradigm in mine industry, it certainly provides additional time to design and permit the final waste dump site and, if well planned, might even result in profit increases by reducing haulage distances in the first years of operation.
id FG-1_b6b8d35c83a0e7f035ec0ad338ad4d10
oai_identifier_str oai:scielo:S2448-167X2021000200253
network_acronym_str FG-1
network_name_str REM - International Engineering Journal
repository_id_str
spelling Multi-stage dumping sequence - a feasible waste management alternative for open pit miningstrategic planningoptimizationsequencingwaste handlingAbstract Waste management and environmental aspects are progressively gathering attention in the mining industry. Mine planners must deal with increasingly complex tasks to balance between ore block schedules, waste disposal, operational cost and environmental reclamation. The mine incomes are generally related to mining and processing of the ore, thus most optimization researches regarding strategic mining usually focus mainly on ore extraction. Nevertheless, waste sequencing and disposal play an important role given that, in several situations in open pit mining, waste volumes are generally larger than ore volumes and must be moved to reach the buried and deeper ore bodies. In some cases, a significant percentage of operational costs is represented by waste haulage and disposal. Thus a careful planning strategy must be considered to minimize unnecessary expenses. Selecting locations for waste dumps is also a challenge. Many operational and technical aspects must be considered, not to mention the increasingly limiting environmental constraints. This definition can be very time consuming, and if it is not properly studied, may negatively impact the mine operation during its lifetime. This article investigates a new approach for mine waste management called the multi-stage dumping sequence (MSDS), suggesting the use of temporary waste dumps along the way to the final dump destination. Although this method requires material re-handling, which is considered a paradigm in mine industry, it certainly provides additional time to design and permit the final waste dump site and, if well planned, might even result in profit increases by reducing haulage distances in the first years of operation.Fundação Gorceix2021-06-01info:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersiontext/htmlhttp://old.scielo.br/scielo.php?script=sci_arttext&pid=S2448-167X2021000200253REM - International Engineering Journal v.74 n.2 2021reponame:REM - International Engineering Journalinstname:Fundação Gorceix (FG)instacron:FG10.1590/0370-44672020740114info:eu-repo/semantics/openAccessKuckartz,Bruno TomasiPeroni,Rodrigo de LemosRodrigues,Áttila Leãeseng2021-03-25T00:00:00Zoai:scielo:S2448-167X2021000200253Revistahttps://www.rem.com.br/?lang=pt-brPRIhttps://old.scielo.br/oai/scielo-oai.php||editor@rem.com.br2448-167X2448-167Xopendoar:2021-03-25T00:00REM - International Engineering Journal - Fundação Gorceix (FG)false
dc.title.none.fl_str_mv Multi-stage dumping sequence - a feasible waste management alternative for open pit mining
title Multi-stage dumping sequence - a feasible waste management alternative for open pit mining
spellingShingle Multi-stage dumping sequence - a feasible waste management alternative for open pit mining
Kuckartz,Bruno Tomasi
strategic planning
optimization
sequencing
waste handling
title_short Multi-stage dumping sequence - a feasible waste management alternative for open pit mining
title_full Multi-stage dumping sequence - a feasible waste management alternative for open pit mining
title_fullStr Multi-stage dumping sequence - a feasible waste management alternative for open pit mining
title_full_unstemmed Multi-stage dumping sequence - a feasible waste management alternative for open pit mining
title_sort Multi-stage dumping sequence - a feasible waste management alternative for open pit mining
author Kuckartz,Bruno Tomasi
author_facet Kuckartz,Bruno Tomasi
Peroni,Rodrigo de Lemos
Rodrigues,Áttila Leães
author_role author
author2 Peroni,Rodrigo de Lemos
Rodrigues,Áttila Leães
author2_role author
author
dc.contributor.author.fl_str_mv Kuckartz,Bruno Tomasi
Peroni,Rodrigo de Lemos
Rodrigues,Áttila Leães
dc.subject.por.fl_str_mv strategic planning
optimization
sequencing
waste handling
topic strategic planning
optimization
sequencing
waste handling
description Abstract Waste management and environmental aspects are progressively gathering attention in the mining industry. Mine planners must deal with increasingly complex tasks to balance between ore block schedules, waste disposal, operational cost and environmental reclamation. The mine incomes are generally related to mining and processing of the ore, thus most optimization researches regarding strategic mining usually focus mainly on ore extraction. Nevertheless, waste sequencing and disposal play an important role given that, in several situations in open pit mining, waste volumes are generally larger than ore volumes and must be moved to reach the buried and deeper ore bodies. In some cases, a significant percentage of operational costs is represented by waste haulage and disposal. Thus a careful planning strategy must be considered to minimize unnecessary expenses. Selecting locations for waste dumps is also a challenge. Many operational and technical aspects must be considered, not to mention the increasingly limiting environmental constraints. This definition can be very time consuming, and if it is not properly studied, may negatively impact the mine operation during its lifetime. This article investigates a new approach for mine waste management called the multi-stage dumping sequence (MSDS), suggesting the use of temporary waste dumps along the way to the final dump destination. Although this method requires material re-handling, which is considered a paradigm in mine industry, it certainly provides additional time to design and permit the final waste dump site and, if well planned, might even result in profit increases by reducing haulage distances in the first years of operation.
publishDate 2021
dc.date.none.fl_str_mv 2021-06-01
dc.type.driver.fl_str_mv info:eu-repo/semantics/article
dc.type.status.fl_str_mv info:eu-repo/semantics/publishedVersion
format article
status_str publishedVersion
dc.identifier.uri.fl_str_mv http://old.scielo.br/scielo.php?script=sci_arttext&pid=S2448-167X2021000200253
url http://old.scielo.br/scielo.php?script=sci_arttext&pid=S2448-167X2021000200253
dc.language.iso.fl_str_mv eng
language eng
dc.relation.none.fl_str_mv 10.1590/0370-44672020740114
dc.rights.driver.fl_str_mv info:eu-repo/semantics/openAccess
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv text/html
dc.publisher.none.fl_str_mv Fundação Gorceix
publisher.none.fl_str_mv Fundação Gorceix
dc.source.none.fl_str_mv REM - International Engineering Journal v.74 n.2 2021
reponame:REM - International Engineering Journal
instname:Fundação Gorceix (FG)
instacron:FG
instname_str Fundação Gorceix (FG)
instacron_str FG
institution FG
reponame_str REM - International Engineering Journal
collection REM - International Engineering Journal
repository.name.fl_str_mv REM - International Engineering Journal - Fundação Gorceix (FG)
repository.mail.fl_str_mv ||editor@rem.com.br
_version_ 1754734691889446912