A contribution to production planning improvement in the construction industry through the anticipation concept

Detalhes bibliográficos
Autor(a) principal: Machado, Ricardo Luiz
Data de Publicação: 2006
Outros Autores: Heineck, Luiz Fernando Mählmann
Tipo de documento: Artigo de conferência
Idioma: eng
Título da fonte: Repositório Institucional da Universidade Federal do Ceará (UFC)
Texto Completo: http://www.repositorio.ufc.br/handle/riufc/7142
Resumo: This article presents a synthesis of a doctorate thesis that proposes a model to improve the production planning process in the construction industry through the systematization of management anticipatory measures. Such systematization is performed through three sequential steps: identification of anticipations that should be present in the production flow; interpretation of what sort of managerial action might be related to the inclusion those anticipations; and due consideration and placing of such management actions in the production planning process. Multiple case studies were conducted on real sites, developing a number of examples of possible anticipatory measures. Most of the time, the lack of proper consideration of such measures was related to problems in the flow of work, thus giving support to the need of improving the building site planning process through this new concept. A number of anticipatory measures are illustrated throughout the text.
id UFC-7_1c5538877f9c7f029348815df542a18b
oai_identifier_str oai:repositorio.ufc.br:riufc/7142
network_acronym_str UFC-7
network_name_str Repositório Institucional da Universidade Federal do Ceará (UFC)
repository_id_str
spelling A contribution to production planning improvement in the construction industry through the anticipation conceptPlanejamento da produçãoIndústria de construção civilThis article presents a synthesis of a doctorate thesis that proposes a model to improve the production planning process in the construction industry through the systematization of management anticipatory measures. Such systematization is performed through three sequential steps: identification of anticipations that should be present in the production flow; interpretation of what sort of managerial action might be related to the inclusion those anticipations; and due consideration and placing of such management actions in the production planning process. Multiple case studies were conducted on real sites, developing a number of examples of possible anticipatory measures. Most of the time, the lack of proper consideration of such measures was related to problems in the flow of work, thus giving support to the need of improving the building site planning process through this new concept. A number of anticipatory measures are illustrated throughout the text.International Conference on Production Research2014-01-14T18:19:17Z2014-01-14T18:19:17Z2006info:eu-repo/semantics/publishedVersioninfo:eu-repo/semantics/conferenceObjectapplication/pdfMACHADO, R. L. ; HEINECK, L. F. M. A contribution to production planning improvement in the construction industry through the anticipation concept. In: INTERNATIONAL CONFERENCE ON PRODUCTION RESEARCH, 3., 2006, Hong Kong. Anais... Hong Kong: ICPR, 2006.http://www.repositorio.ufc.br/handle/riufc/7142Machado, Ricardo LuizHeineck, Luiz Fernando Mählmannengreponame:Repositório Institucional da Universidade Federal do Ceará (UFC)instname:Universidade Federal do Ceará (UFC)instacron:UFCinfo:eu-repo/semantics/openAccess2023-03-24T13:40:15Zoai:repositorio.ufc.br:riufc/7142Repositório InstitucionalPUBhttp://www.repositorio.ufc.br/ri-oai/requestbu@ufc.br || repositorio@ufc.bropendoar:2024-09-11T18:42:06.325365Repositório Institucional da Universidade Federal do Ceará (UFC) - Universidade Federal do Ceará (UFC)false
dc.title.none.fl_str_mv A contribution to production planning improvement in the construction industry through the anticipation concept
title A contribution to production planning improvement in the construction industry through the anticipation concept
spellingShingle A contribution to production planning improvement in the construction industry through the anticipation concept
Machado, Ricardo Luiz
Planejamento da produção
Indústria de construção civil
title_short A contribution to production planning improvement in the construction industry through the anticipation concept
title_full A contribution to production planning improvement in the construction industry through the anticipation concept
title_fullStr A contribution to production planning improvement in the construction industry through the anticipation concept
title_full_unstemmed A contribution to production planning improvement in the construction industry through the anticipation concept
title_sort A contribution to production planning improvement in the construction industry through the anticipation concept
author Machado, Ricardo Luiz
author_facet Machado, Ricardo Luiz
Heineck, Luiz Fernando Mählmann
author_role author
author2 Heineck, Luiz Fernando Mählmann
author2_role author
dc.contributor.author.fl_str_mv Machado, Ricardo Luiz
Heineck, Luiz Fernando Mählmann
dc.subject.por.fl_str_mv Planejamento da produção
Indústria de construção civil
topic Planejamento da produção
Indústria de construção civil
description This article presents a synthesis of a doctorate thesis that proposes a model to improve the production planning process in the construction industry through the systematization of management anticipatory measures. Such systematization is performed through three sequential steps: identification of anticipations that should be present in the production flow; interpretation of what sort of managerial action might be related to the inclusion those anticipations; and due consideration and placing of such management actions in the production planning process. Multiple case studies were conducted on real sites, developing a number of examples of possible anticipatory measures. Most of the time, the lack of proper consideration of such measures was related to problems in the flow of work, thus giving support to the need of improving the building site planning process through this new concept. A number of anticipatory measures are illustrated throughout the text.
publishDate 2006
dc.date.none.fl_str_mv 2006
2014-01-14T18:19:17Z
2014-01-14T18:19:17Z
dc.type.status.fl_str_mv info:eu-repo/semantics/publishedVersion
dc.type.driver.fl_str_mv info:eu-repo/semantics/conferenceObject
format conferenceObject
status_str publishedVersion
dc.identifier.uri.fl_str_mv MACHADO, R. L. ; HEINECK, L. F. M. A contribution to production planning improvement in the construction industry through the anticipation concept. In: INTERNATIONAL CONFERENCE ON PRODUCTION RESEARCH, 3., 2006, Hong Kong. Anais... Hong Kong: ICPR, 2006.
http://www.repositorio.ufc.br/handle/riufc/7142
identifier_str_mv MACHADO, R. L. ; HEINECK, L. F. M. A contribution to production planning improvement in the construction industry through the anticipation concept. In: INTERNATIONAL CONFERENCE ON PRODUCTION RESEARCH, 3., 2006, Hong Kong. Anais... Hong Kong: ICPR, 2006.
url http://www.repositorio.ufc.br/handle/riufc/7142
dc.language.iso.fl_str_mv eng
language eng
dc.rights.driver.fl_str_mv info:eu-repo/semantics/openAccess
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv application/pdf
dc.publisher.none.fl_str_mv International Conference on Production Research
publisher.none.fl_str_mv International Conference on Production Research
dc.source.none.fl_str_mv reponame:Repositório Institucional da Universidade Federal do Ceará (UFC)
instname:Universidade Federal do Ceará (UFC)
instacron:UFC
instname_str Universidade Federal do Ceará (UFC)
instacron_str UFC
institution UFC
reponame_str Repositório Institucional da Universidade Federal do Ceará (UFC)
collection Repositório Institucional da Universidade Federal do Ceará (UFC)
repository.name.fl_str_mv Repositório Institucional da Universidade Federal do Ceará (UFC) - Universidade Federal do Ceará (UFC)
repository.mail.fl_str_mv bu@ufc.br || repositorio@ufc.br
_version_ 1813028912210378752