Preplanning method for multistore building construction using line of balance
Autor(a) principal: | |
---|---|
Data de Publicação: | 1998 |
Outros Autores: | |
Tipo de documento: | Artigo de conferência |
Idioma: | eng |
Título da fonte: | Repositório Institucional da Universidade Federal do Ceará (UFC) |
Texto Completo: | http://www.repositorio.ufc.br/handle/riufc/8146 |
Resumo: | This paper reports one aspect of a research program devoted to the topic of production control in multi-story building construction. Preplanning using the line of balance technique attempts to solve planning problems by making production process clearer and simpler. A preplanning method is presented which needs little detailed information about productivities and work volumes and may be rapidly produced. The plan brings an overall view of the project by grouping the main activities that are highly interdependent. The concept on the best rhythm for each group of activities focus on the sequencie of work, continuity of labor team working and completeness rather than on pure schedule goals. Many characteristics of the method support lean construction concepts, such as waste elimination, variances minimization, flexible planning and scheduling sequencing. Using line of balance concepts also suggests some control tools which are being experimented on aplication cases and are briefly described. |
id |
UFC-7_72ccc67323ac7aa31adc7225de253722 |
---|---|
oai_identifier_str |
oai:repositorio.ufc.br:riufc/8146 |
network_acronym_str |
UFC-7 |
network_name_str |
Repositório Institucional da Universidade Federal do Ceará (UFC) |
repository_id_str |
|
spelling |
Preplanning method for multistore building construction using line of balanceConstrução civil - PlanejamentoControle de produçãoConstrução enxutaThis paper reports one aspect of a research program devoted to the topic of production control in multi-story building construction. Preplanning using the line of balance technique attempts to solve planning problems by making production process clearer and simpler. A preplanning method is presented which needs little detailed information about productivities and work volumes and may be rapidly produced. The plan brings an overall view of the project by grouping the main activities that are highly interdependent. The concept on the best rhythm for each group of activities focus on the sequencie of work, continuity of labor team working and completeness rather than on pure schedule goals. Many characteristics of the method support lean construction concepts, such as waste elimination, variances minimization, flexible planning and scheduling sequencing. Using line of balance concepts also suggests some control tools which are being experimented on aplication cases and are briefly described.2014-05-30T19:06:16Z2014-05-30T19:06:16Z1998info:eu-repo/semantics/publishedVersioninfo:eu-repo/semantics/conferenceObjectapplication/pdfMENDES JUNIOR, R. ; HEINECK, L. F. M. Preplanning method for multistore building construction using line of balance. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 6., 1998, Guarujá. Anais... Guarujá: IGLC, 1998.http://www.repositorio.ufc.br/handle/riufc/8146Mendes Júnior, RicardoHeineck, Luiz Fernando Mählmannengreponame:Repositório Institucional da Universidade Federal do Ceará (UFC)instname:Universidade Federal do Ceará (UFC)instacron:UFCinfo:eu-repo/semantics/openAccess2020-08-31T18:40:11Zoai:repositorio.ufc.br:riufc/8146Repositório InstitucionalPUBhttp://www.repositorio.ufc.br/ri-oai/requestbu@ufc.br || repositorio@ufc.bropendoar:2024-09-11T18:27:16.626376Repositório Institucional da Universidade Federal do Ceará (UFC) - Universidade Federal do Ceará (UFC)false |
dc.title.none.fl_str_mv |
Preplanning method for multistore building construction using line of balance |
title |
Preplanning method for multistore building construction using line of balance |
spellingShingle |
Preplanning method for multistore building construction using line of balance Mendes Júnior, Ricardo Construção civil - Planejamento Controle de produção Construção enxuta |
title_short |
Preplanning method for multistore building construction using line of balance |
title_full |
Preplanning method for multistore building construction using line of balance |
title_fullStr |
Preplanning method for multistore building construction using line of balance |
title_full_unstemmed |
Preplanning method for multistore building construction using line of balance |
title_sort |
Preplanning method for multistore building construction using line of balance |
author |
Mendes Júnior, Ricardo |
author_facet |
Mendes Júnior, Ricardo Heineck, Luiz Fernando Mählmann |
author_role |
author |
author2 |
Heineck, Luiz Fernando Mählmann |
author2_role |
author |
dc.contributor.author.fl_str_mv |
Mendes Júnior, Ricardo Heineck, Luiz Fernando Mählmann |
dc.subject.por.fl_str_mv |
Construção civil - Planejamento Controle de produção Construção enxuta |
topic |
Construção civil - Planejamento Controle de produção Construção enxuta |
description |
This paper reports one aspect of a research program devoted to the topic of production control in multi-story building construction. Preplanning using the line of balance technique attempts to solve planning problems by making production process clearer and simpler. A preplanning method is presented which needs little detailed information about productivities and work volumes and may be rapidly produced. The plan brings an overall view of the project by grouping the main activities that are highly interdependent. The concept on the best rhythm for each group of activities focus on the sequencie of work, continuity of labor team working and completeness rather than on pure schedule goals. Many characteristics of the method support lean construction concepts, such as waste elimination, variances minimization, flexible planning and scheduling sequencing. Using line of balance concepts also suggests some control tools which are being experimented on aplication cases and are briefly described. |
publishDate |
1998 |
dc.date.none.fl_str_mv |
1998 2014-05-30T19:06:16Z 2014-05-30T19:06:16Z |
dc.type.status.fl_str_mv |
info:eu-repo/semantics/publishedVersion |
dc.type.driver.fl_str_mv |
info:eu-repo/semantics/conferenceObject |
format |
conferenceObject |
status_str |
publishedVersion |
dc.identifier.uri.fl_str_mv |
MENDES JUNIOR, R. ; HEINECK, L. F. M. Preplanning method for multistore building construction using line of balance. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 6., 1998, Guarujá. Anais... Guarujá: IGLC, 1998. http://www.repositorio.ufc.br/handle/riufc/8146 |
identifier_str_mv |
MENDES JUNIOR, R. ; HEINECK, L. F. M. Preplanning method for multistore building construction using line of balance. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION, 6., 1998, Guarujá. Anais... Guarujá: IGLC, 1998. |
url |
http://www.repositorio.ufc.br/handle/riufc/8146 |
dc.language.iso.fl_str_mv |
eng |
language |
eng |
dc.rights.driver.fl_str_mv |
info:eu-repo/semantics/openAccess |
eu_rights_str_mv |
openAccess |
dc.format.none.fl_str_mv |
application/pdf |
dc.source.none.fl_str_mv |
reponame:Repositório Institucional da Universidade Federal do Ceará (UFC) instname:Universidade Federal do Ceará (UFC) instacron:UFC |
instname_str |
Universidade Federal do Ceará (UFC) |
instacron_str |
UFC |
institution |
UFC |
reponame_str |
Repositório Institucional da Universidade Federal do Ceará (UFC) |
collection |
Repositório Institucional da Universidade Federal do Ceará (UFC) |
repository.name.fl_str_mv |
Repositório Institucional da Universidade Federal do Ceará (UFC) - Universidade Federal do Ceará (UFC) |
repository.mail.fl_str_mv |
bu@ufc.br || repositorio@ufc.br |
_version_ |
1813028810479632384 |