Priorização de medidas de prevenção pela utilização da ferramenta FMEA na análise de riscos na construção civil

Detalhes bibliográficos
Autor(a) principal: Zaupa, Juliana Caroline Teixeira
Data de Publicação: 2023
Outros Autores: Catai, Rodrigo Eduardo, Corrêa, Janine Nicolosi, Zaupa, Julio Cesar
Tipo de documento: Artigo
Idioma: por
eng
spa
Título da fonte: Brazilian Journal of Production Engineering
Texto Completo: https://periodicos.ufes.br/bjpe/article/view/40211
Resumo: According to Social Security statistics for 2021, the number of accidents at work in Brazil remains high, with 34,000 belonging to the construction sector this year. In this scenario, risk management has high importance in risk analysis for accident prevention. Focusing on this issue, this research was carried out in the civil construction sector between the years 2021 and 2022, with the general objective of prioritizing preventive measures related to work safety in civil construction, verified by the use of the Failure Modes and Effects Analysis (FMEA) tool. In order to obtain data, observational and photographic records were made in the work analyzed in relation to the risks to which workers are exposed. Subsequently, the risk priority analysis was carried out using the FMEA tool. Among the high-Risk Priority Numbers (RPNs) there is the non-use of personal protective equipment, a serious situation due to its high risk. Thus, it can be concluded that the FMEA method contributed to the prioritization of preventive measures related to work safety for the analyzed civil construction work.
id UFES-11_b8e9865ddbde470257e65137fd3bd26b
oai_identifier_str oai:periodicos.ufes.br:article/40211
network_acronym_str UFES-11
network_name_str Brazilian Journal of Production Engineering
repository_id_str
spelling Priorização de medidas de prevenção pela utilização da ferramenta FMEA na análise de riscos na construção civilPrioritization of preventive measures by using the FMEA tool in risk analysis in civil constructionPriorización de medidas de prevención mediante el uso de la herramienta FMEA en el análisis de riesgos en la construcción civilSegurança do trabalhoconstrução civilFMEAWorkplace safetyconstructionFMEASeguridad de trabajoconstrucción civilFMEAAccording to Social Security statistics for 2021, the number of accidents at work in Brazil remains high, with 34,000 belonging to the construction sector this year. In this scenario, risk management has high importance in risk analysis for accident prevention. Focusing on this issue, this research was carried out in the civil construction sector between the years 2021 and 2022, with the general objective of prioritizing preventive measures related to work safety in civil construction, verified by the use of the Failure Modes and Effects Analysis (FMEA) tool. In order to obtain data, observational and photographic records were made in the work analyzed in relation to the risks to which workers are exposed. Subsequently, the risk priority analysis was carried out using the FMEA tool. Among the high-Risk Priority Numbers (RPNs) there is the non-use of personal protective equipment, a serious situation due to its high risk. Thus, it can be concluded that the FMEA method contributed to the prioritization of preventive measures related to work safety for the analyzed civil construction work.Según las estadísticas de la Seguridad Social para 2021, el número de accidentes de trabajo en Brasil sigue siendo alto, con 34.000 pertenecientes al sector de la construcción este año. En este escenario, la gestión de riesgos tiene una gran importancia en el análisis de riesgos para la prevención de accidentes. Centrándose en este tema, esta investigación se llevó a cabo en el sector de la construcción civil entre los años 2021 y 2022, con el objetivo general de priorizar las medidas preventivas relacionadas con la seguridad en el trabajo, verificado mediante el uso de la herramienta Análisis de Modos y Efectos de Falla - FMEA (Análisis Modo y Efecto de Falla), para una obra de construcción civil. Para la obtención de datos se realizaron registros observacionales y fotográficos en los trabajos analizados en relación a los riesgos a los que están expuestos los trabajadores. Posteriormente se realizó el análisis de prioridad de riesgos mediante la herramienta FMEA, y entre los RPN (Risk Priority Numbers) altos se encuentra la no utilización de equipos de protección personal, situación grave por su alto riesgo. Así, se puede concluir que el método FMEA contribuyó a la priorización de medidas preventivas relacionadas con la seguridad en el trabajo para la obra de construcción civil analizada.De acordo com estatísticas da Previdência Social de 2021, o número de acidentes do trabalho no Brasil permanece elevado, sendo que neste ano 34 mil pertencem ao setor da construção.  Neste cenário, o gerenciamento de riscos tem elevada importância na análise de riscos para a prevenção de acidentes. Com foco nesta questão, esta pesquisa foi realizada no setor da construção civil entre os anos de 2021 e 2022, tendo como objetivo geral priorizar medidas de prevenção relativas a segurança do trabalho, constatadas pela utilização da ferramenta Análise de Modos de Falhas e Efeitos - FMEA (Failure Mode and Effect Analysis), para uma obra de construção civil. Para a obtenção de dados, foram realizados registros observacionais e fotográficos na obra analisada em relação aos riscos aos quais estão expostos os trabalhadores. Posteriormente, foi realizada a análise da prioridade de riscos com a utilização da ferramenta FMEA, sendo que entre os elevados RPNs (Números de Prioridade de Risco) está a não utilização de equipamentos de proteção individual, situação grave por apresentar alto risco. Assim, pôde-se concluir que o método FMEA contribuiu para a priorização de medidas de prevenção relativas a segurança do trabalho para a obra de construção civil analisada.Universidade Federal do Espírito Santo - UFES2023-05-02info:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersionArtigo avaliado pelos paresapplication/pdfapplication/pdfimage/jpegimage/jpegimage/jpegaudio/mpegaudio/mpeghttps://periodicos.ufes.br/bjpe/article/view/4021110.47456/bjpe.v9i2.40211Brazilian Journal of Production Engineering; Vol. 9 No. 2 (2023): Regular Issue (April - June) *Publication Articles Continuous Flow*; 14-26Brazilian Journal of Production Engineering; Vol. 9 Núm. 2 (2023): Edición regular (abril - junio) *Artículos de publicación Flujo continuo*; 14-26Brazilian Journal of Production Engineering; v. 9 n. 2 (2023): Número Regular (Abril - Junho); 14-262447-558010.47456/bjpe.v9i2reponame:Brazilian Journal of Production Engineeringinstname:Universidade Federal do Espírito Santo (UFES)instacron:UFESporengspahttps://periodicos.ufes.br/bjpe/article/view/40211/27120https://periodicos.ufes.br/bjpe/article/view/40211/27223https://periodicos.ufes.br/bjpe/article/view/40211/27008https://periodicos.ufes.br/bjpe/article/view/40211/27009https://periodicos.ufes.br/bjpe/article/view/40211/27010https://periodicos.ufes.br/bjpe/article/view/40211/27011https://periodicos.ufes.br/bjpe/article/view/40211/27012https://periodicos.ufes.br/bjpe/article/view/40211/27154Copyright (c) 2023 Brazilian Journal of Production Engineeringhttps://creativecommons.org/licenses/by-nc-sa/4.0info:eu-repo/semantics/openAccessZaupa, Juliana Caroline TeixeiraCatai, Rodrigo EduardoCorrêa, Janine NicolosiZaupa, Julio Cesar2023-09-29T17:29:46Zoai:periodicos.ufes.br:article/40211Revistahttps://periodicos.ufes.br/bjpePUBhttps://periodicos.ufes.br/bjpe/oairodrigo.r.freitas@ufes.br2447-55802447-5580opendoar:2023-09-29T17:29:46Brazilian Journal of Production Engineering - Universidade Federal do Espírito Santo (UFES)false
dc.title.none.fl_str_mv Priorização de medidas de prevenção pela utilização da ferramenta FMEA na análise de riscos na construção civil
Prioritization of preventive measures by using the FMEA tool in risk analysis in civil construction
Priorización de medidas de prevención mediante el uso de la herramienta FMEA en el análisis de riesgos en la construcción civil
title Priorização de medidas de prevenção pela utilização da ferramenta FMEA na análise de riscos na construção civil
spellingShingle Priorização de medidas de prevenção pela utilização da ferramenta FMEA na análise de riscos na construção civil
Zaupa, Juliana Caroline Teixeira
Segurança do trabalho
construção civil
FMEA
Workplace safety
construction
FMEA
Seguridad de trabajo
construcción civil
FMEA
title_short Priorização de medidas de prevenção pela utilização da ferramenta FMEA na análise de riscos na construção civil
title_full Priorização de medidas de prevenção pela utilização da ferramenta FMEA na análise de riscos na construção civil
title_fullStr Priorização de medidas de prevenção pela utilização da ferramenta FMEA na análise de riscos na construção civil
title_full_unstemmed Priorização de medidas de prevenção pela utilização da ferramenta FMEA na análise de riscos na construção civil
title_sort Priorização de medidas de prevenção pela utilização da ferramenta FMEA na análise de riscos na construção civil
author Zaupa, Juliana Caroline Teixeira
author_facet Zaupa, Juliana Caroline Teixeira
Catai, Rodrigo Eduardo
Corrêa, Janine Nicolosi
Zaupa, Julio Cesar
author_role author
author2 Catai, Rodrigo Eduardo
Corrêa, Janine Nicolosi
Zaupa, Julio Cesar
author2_role author
author
author
dc.contributor.author.fl_str_mv Zaupa, Juliana Caroline Teixeira
Catai, Rodrigo Eduardo
Corrêa, Janine Nicolosi
Zaupa, Julio Cesar
dc.subject.por.fl_str_mv Segurança do trabalho
construção civil
FMEA
Workplace safety
construction
FMEA
Seguridad de trabajo
construcción civil
FMEA
topic Segurança do trabalho
construção civil
FMEA
Workplace safety
construction
FMEA
Seguridad de trabajo
construcción civil
FMEA
description According to Social Security statistics for 2021, the number of accidents at work in Brazil remains high, with 34,000 belonging to the construction sector this year. In this scenario, risk management has high importance in risk analysis for accident prevention. Focusing on this issue, this research was carried out in the civil construction sector between the years 2021 and 2022, with the general objective of prioritizing preventive measures related to work safety in civil construction, verified by the use of the Failure Modes and Effects Analysis (FMEA) tool. In order to obtain data, observational and photographic records were made in the work analyzed in relation to the risks to which workers are exposed. Subsequently, the risk priority analysis was carried out using the FMEA tool. Among the high-Risk Priority Numbers (RPNs) there is the non-use of personal protective equipment, a serious situation due to its high risk. Thus, it can be concluded that the FMEA method contributed to the prioritization of preventive measures related to work safety for the analyzed civil construction work.
publishDate 2023
dc.date.none.fl_str_mv 2023-05-02
dc.type.driver.fl_str_mv info:eu-repo/semantics/article
info:eu-repo/semantics/publishedVersion
Artigo avaliado pelos pares
format article
status_str publishedVersion
dc.identifier.uri.fl_str_mv https://periodicos.ufes.br/bjpe/article/view/40211
10.47456/bjpe.v9i2.40211
url https://periodicos.ufes.br/bjpe/article/view/40211
identifier_str_mv 10.47456/bjpe.v9i2.40211
dc.language.iso.fl_str_mv por
eng
spa
language por
eng
spa
dc.relation.none.fl_str_mv https://periodicos.ufes.br/bjpe/article/view/40211/27120
https://periodicos.ufes.br/bjpe/article/view/40211/27223
https://periodicos.ufes.br/bjpe/article/view/40211/27008
https://periodicos.ufes.br/bjpe/article/view/40211/27009
https://periodicos.ufes.br/bjpe/article/view/40211/27010
https://periodicos.ufes.br/bjpe/article/view/40211/27011
https://periodicos.ufes.br/bjpe/article/view/40211/27012
https://periodicos.ufes.br/bjpe/article/view/40211/27154
dc.rights.driver.fl_str_mv Copyright (c) 2023 Brazilian Journal of Production Engineering
https://creativecommons.org/licenses/by-nc-sa/4.0
info:eu-repo/semantics/openAccess
rights_invalid_str_mv Copyright (c) 2023 Brazilian Journal of Production Engineering
https://creativecommons.org/licenses/by-nc-sa/4.0
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv application/pdf
application/pdf
image/jpeg
image/jpeg
image/jpeg
audio/mpeg
audio/mpeg
dc.publisher.none.fl_str_mv Universidade Federal do Espírito Santo - UFES
publisher.none.fl_str_mv Universidade Federal do Espírito Santo - UFES
dc.source.none.fl_str_mv Brazilian Journal of Production Engineering; Vol. 9 No. 2 (2023): Regular Issue (April - June) *Publication Articles Continuous Flow*; 14-26
Brazilian Journal of Production Engineering; Vol. 9 Núm. 2 (2023): Edición regular (abril - junio) *Artículos de publicación Flujo continuo*; 14-26
Brazilian Journal of Production Engineering; v. 9 n. 2 (2023): Número Regular (Abril - Junho); 14-26
2447-5580
10.47456/bjpe.v9i2
reponame:Brazilian Journal of Production Engineering
instname:Universidade Federal do Espírito Santo (UFES)
instacron:UFES
instname_str Universidade Federal do Espírito Santo (UFES)
instacron_str UFES
institution UFES
reponame_str Brazilian Journal of Production Engineering
collection Brazilian Journal of Production Engineering
repository.name.fl_str_mv Brazilian Journal of Production Engineering - Universidade Federal do Espírito Santo (UFES)
repository.mail.fl_str_mv rodrigo.r.freitas@ufes.br
_version_ 1797047317755330560