Metodologia de implantação da construção enxuta: estudo de caso em construtora de porte médio

Detalhes bibliográficos
Autor(a) principal: Oliveira, Erikson Ricardo Marques de
Data de Publicação: 2013
Tipo de documento: Dissertação
Idioma: por
Título da fonte: Repositório Institucional da UFRN
Texto Completo: https://repositorio.ufrn.br/jspui/handle/123456789/14848
Resumo: In recent years, the Brazilian construction industry has gone by changes like currency stability, increasing competition, shortage of skilled labor and increasing quality importance required by the customer, who made the sector companies seek solutions through new management practices in order to become more efficient. A alternative to these management practices is known as Lean Construction which is derived from the Toyota System Production. Lean Construction main goals are to reduce parts of activities that do not add value, increase product value by considering customer needs, reduce variability and production cycle time, simplify process by reducing the number of parts or steps, increase the flexibility in the product execution and transparency process, focus the control on overall process, introduce continuous improvement process, maintain a balance between improvements in flows and conversions and seek to learn from practices adopted by competitors. However, the construction industry is characterized by having nomadic activity, which undertakes an unique product with high cost of production and big inertia for behavioral change, making it difficult to implement the philosophy of lean construction in companies. In this sense, the main objective of this study is to develop a methodology for implementation of the principles of Lean Construction. The method of implementing the proposed management system was designed with the aid of 5W2H tool, and the implementation process is divided into three phases. The first one aims to know in a macro way the current operation of construction, identify who is its target audience and what are the products and services offered to the Market. The second phase aims to describe what actions should be taken and which documents are needed to be created or modified; finally, the third step goal consists in how to control and monitor established processes, where through Strategic Planning the company goals would be set along with their respective targets and indicators in order to keep the system working, aiming for continuous improvement with focus on the customer. This methodology was conceived as a case study analyzing a medium size construction with more than 18 years of activity and certified for almost 10 years with ISO9001 and level A in PBQP-H. We also conclude that this implementation process can be used in any developer and / or builder
id UFRN_3a8f7c05888e29b8c9c63f1eb15e4847
oai_identifier_str oai:https://repositorio.ufrn.br:123456789/14848
network_acronym_str UFRN
network_name_str Repositório Institucional da UFRN
repository_id_str
spelling Oliveira, Erikson Ricardo Marques dehttp://lattes.cnpq.br/3059741124423296http://lattes.cnpq.br/7590200701773198Almeida, Mariana Rodrigues dehttp://lattes.cnpq.br/7356242205950550Silva, Alessandro Lucas dahttp://lattes.cnpq.br/6058119214477061Almeida, Maria das Vitórias Vieira de2014-12-17T14:48:15Z2014-04-142014-12-17T14:48:15Z2013-08-16OLIVEIRA, Erikson Ricardo Marques de. Metodologia de implantação da construção enxuta: estudo de caso em construtora de porte médio. 2013. 175 f. Dissertação (Mestrado em MECÂNICA DAS ESTRUTURAS, ESTRUTURAS DE CONCRETO E ALVENARIA E MATERIAIS E PROCESSOS CONSTRUTIVOS) - Universidade Federal do Rio Grande do Norte, Natal, 2013.https://repositorio.ufrn.br/jspui/handle/123456789/14848In recent years, the Brazilian construction industry has gone by changes like currency stability, increasing competition, shortage of skilled labor and increasing quality importance required by the customer, who made the sector companies seek solutions through new management practices in order to become more efficient. A alternative to these management practices is known as Lean Construction which is derived from the Toyota System Production. Lean Construction main goals are to reduce parts of activities that do not add value, increase product value by considering customer needs, reduce variability and production cycle time, simplify process by reducing the number of parts or steps, increase the flexibility in the product execution and transparency process, focus the control on overall process, introduce continuous improvement process, maintain a balance between improvements in flows and conversions and seek to learn from practices adopted by competitors. However, the construction industry is characterized by having nomadic activity, which undertakes an unique product with high cost of production and big inertia for behavioral change, making it difficult to implement the philosophy of lean construction in companies. In this sense, the main objective of this study is to develop a methodology for implementation of the principles of Lean Construction. The method of implementing the proposed management system was designed with the aid of 5W2H tool, and the implementation process is divided into three phases. The first one aims to know in a macro way the current operation of construction, identify who is its target audience and what are the products and services offered to the Market. The second phase aims to describe what actions should be taken and which documents are needed to be created or modified; finally, the third step goal consists in how to control and monitor established processes, where through Strategic Planning the company goals would be set along with their respective targets and indicators in order to keep the system working, aiming for continuous improvement with focus on the customer. This methodology was conceived as a case study analyzing a medium size construction with more than 18 years of activity and certified for almost 10 years with ISO9001 and level A in PBQP-H. We also conclude that this implementation process can be used in any developer and / or builderA construção civil brasileira, nos últimos anos, tem passado por mudanças como estabilidade da moeda, aumento da concorrência, escassez de mão de obra qualificada e aumento da importância da qualidade requerida pelo cliente, obrigando que as empresas do setor procurem soluções através de novas práticas de gestão, buscando se tornarem mais eficientes. Uma alternativa dessas práticas de gestão é conhecida como construção enxuta (Lean Construction), sendo derivada do Sistema Toyota de Produção. A construção enxuta visa a reduzir a parcela de atividades que não agregam valor, aumentar o valor do produto através da consideração das necessidades do cliente, reduzir a variabilidade e o tempo do ciclo de produção, simplificar o processo através da redução do número de passos ou partes, aumentar a flexibilidade na execução do produto e a transparência do processo, focar o controle no processo global, introduzir melhoria contínua no processo, manter um equilíbrio entre melhorias nos fluxos e nas conversões e, ainda, buscar aprender com as práticas adotadas pelas empresas concorrentes. A indústria da construção civil é caracterizada por possuir atividade nômade, que empreende produto único, com custo elevado de produção e grande inércia para mudança comportamental; desse modo, torna-se difícil a implantação da filosofia da construção enxuta nas empresas. Sendo assim, buscando facilitar a aplicabilidade da construção enxuta nas empresas, o objetivo principal deste trabalho é elaborar uma metodologia de implantação dos princípios desta nova filosofia de gestão. O método de implantação do sistema de gestão proposto foi concebido com auxílio da ferramenta 5W2H, tendo o processo de implantação dividido em três etapas, sendo a primeira com a finalidade de elaborar diagnóstico da empresa, visando a entender o funcionamento da construtora, identificando qual é seu público-alvo e quais são os produtos e os serviços oferecidos por esta ao mercado. A segunda etapa consiste em descrever quais ações devem ser tomadas e quais documentos precisam ser criados ou modificados; e, por fim, a meta da terceira etapa compreende como controlar e acompanhar os processos estabelecidos, extraindo do planejamento estratégico os objetivos da empresa com suas respectivas metas e indicadores com a finalidade de manter o sistema funcionando e almejando a melhoria contínua com foco no cliente. A presente metodologia foi concebida utilizando como estudo de caso uma construtora de porte médio com mais de 18 anos de atividade e certificada há quase 10 anos com a ISO9001 e nível A do PBQP-H. Conclui-se, ainda, que esse processo de implantação possa ser utilizado em qualquer incorporadora e/ou construtora do segmento da construçãoapplication/pdfporUniversidade Federal do Rio Grande do NortePrograma de Pós-Graduação em Engenharia CivilUFRNBRMECÂNICA DAS ESTRUTURAS, ESTRUTURAS DE CONCRETO E ALVENARIA E MATERIAIS E PROCESSOS CONSTRUTIVOSConstrução civil. Gestão de qualidade. Construção enxutaCivil construction. Quality management. Lean constructionCNPQ::ENGENHARIAS::ENGENHARIA CIVILMetodologia de implantação da construção enxuta: estudo de caso em construtora de porte médioinfo:eu-repo/semantics/publishedVersioninfo:eu-repo/semantics/masterThesisinfo:eu-repo/semantics/openAccessreponame:Repositório Institucional da UFRNinstname:Universidade Federal do Rio Grande do Norte (UFRN)instacron:UFRNORIGINALEriksonRMO_DISSERT.pdfapplication/pdf2593729https://repositorio.ufrn.br/bitstream/123456789/14848/1/EriksonRMO_DISSERT.pdfe7be854fab647e1f1602ce7096cdca4cMD51TEXTEriksonRMO_DISSERT.pdf.txtEriksonRMO_DISSERT.pdf.txtExtracted texttext/plain304237https://repositorio.ufrn.br/bitstream/123456789/14848/6/EriksonRMO_DISSERT.pdf.txt35831641c699f979e9f0d42db683f18cMD56THUMBNAILEriksonRMO_DISSERT.pdf.jpgEriksonRMO_DISSERT.pdf.jpgIM Thumbnailimage/jpeg3197https://repositorio.ufrn.br/bitstream/123456789/14848/7/EriksonRMO_DISSERT.pdf.jpga340f2298463864231f4954688396411MD57123456789/148482017-11-02 00:06:16.404oai:https://repositorio.ufrn.br:123456789/14848Repositório de PublicaçõesPUBhttp://repositorio.ufrn.br/oai/opendoar:2017-11-02T03:06:16Repositório Institucional da UFRN - Universidade Federal do Rio Grande do Norte (UFRN)false
dc.title.por.fl_str_mv Metodologia de implantação da construção enxuta: estudo de caso em construtora de porte médio
title Metodologia de implantação da construção enxuta: estudo de caso em construtora de porte médio
spellingShingle Metodologia de implantação da construção enxuta: estudo de caso em construtora de porte médio
Oliveira, Erikson Ricardo Marques de
Construção civil. Gestão de qualidade. Construção enxuta
Civil construction. Quality management. Lean construction
CNPQ::ENGENHARIAS::ENGENHARIA CIVIL
title_short Metodologia de implantação da construção enxuta: estudo de caso em construtora de porte médio
title_full Metodologia de implantação da construção enxuta: estudo de caso em construtora de porte médio
title_fullStr Metodologia de implantação da construção enxuta: estudo de caso em construtora de porte médio
title_full_unstemmed Metodologia de implantação da construção enxuta: estudo de caso em construtora de porte médio
title_sort Metodologia de implantação da construção enxuta: estudo de caso em construtora de porte médio
author Oliveira, Erikson Ricardo Marques de
author_facet Oliveira, Erikson Ricardo Marques de
author_role author
dc.contributor.authorID.por.fl_str_mv
dc.contributor.authorLattes.por.fl_str_mv http://lattes.cnpq.br/3059741124423296
dc.contributor.advisorID.por.fl_str_mv
dc.contributor.advisorLattes.por.fl_str_mv http://lattes.cnpq.br/7590200701773198
dc.contributor.referees1.pt_BR.fl_str_mv Almeida, Mariana Rodrigues de
dc.contributor.referees1ID.por.fl_str_mv
dc.contributor.referees1Lattes.por.fl_str_mv http://lattes.cnpq.br/7356242205950550
dc.contributor.referees2.pt_BR.fl_str_mv Silva, Alessandro Lucas da
dc.contributor.referees2ID.por.fl_str_mv
dc.contributor.referees2Lattes.por.fl_str_mv http://lattes.cnpq.br/6058119214477061
dc.contributor.author.fl_str_mv Oliveira, Erikson Ricardo Marques de
dc.contributor.advisor1.fl_str_mv Almeida, Maria das Vitórias Vieira de
contributor_str_mv Almeida, Maria das Vitórias Vieira de
dc.subject.por.fl_str_mv Construção civil. Gestão de qualidade. Construção enxuta
topic Construção civil. Gestão de qualidade. Construção enxuta
Civil construction. Quality management. Lean construction
CNPQ::ENGENHARIAS::ENGENHARIA CIVIL
dc.subject.eng.fl_str_mv Civil construction. Quality management. Lean construction
dc.subject.cnpq.fl_str_mv CNPQ::ENGENHARIAS::ENGENHARIA CIVIL
description In recent years, the Brazilian construction industry has gone by changes like currency stability, increasing competition, shortage of skilled labor and increasing quality importance required by the customer, who made the sector companies seek solutions through new management practices in order to become more efficient. A alternative to these management practices is known as Lean Construction which is derived from the Toyota System Production. Lean Construction main goals are to reduce parts of activities that do not add value, increase product value by considering customer needs, reduce variability and production cycle time, simplify process by reducing the number of parts or steps, increase the flexibility in the product execution and transparency process, focus the control on overall process, introduce continuous improvement process, maintain a balance between improvements in flows and conversions and seek to learn from practices adopted by competitors. However, the construction industry is characterized by having nomadic activity, which undertakes an unique product with high cost of production and big inertia for behavioral change, making it difficult to implement the philosophy of lean construction in companies. In this sense, the main objective of this study is to develop a methodology for implementation of the principles of Lean Construction. The method of implementing the proposed management system was designed with the aid of 5W2H tool, and the implementation process is divided into three phases. The first one aims to know in a macro way the current operation of construction, identify who is its target audience and what are the products and services offered to the Market. The second phase aims to describe what actions should be taken and which documents are needed to be created or modified; finally, the third step goal consists in how to control and monitor established processes, where through Strategic Planning the company goals would be set along with their respective targets and indicators in order to keep the system working, aiming for continuous improvement with focus on the customer. This methodology was conceived as a case study analyzing a medium size construction with more than 18 years of activity and certified for almost 10 years with ISO9001 and level A in PBQP-H. We also conclude that this implementation process can be used in any developer and / or builder
publishDate 2013
dc.date.issued.fl_str_mv 2013-08-16
dc.date.accessioned.fl_str_mv 2014-12-17T14:48:15Z
dc.date.available.fl_str_mv 2014-04-14
2014-12-17T14:48:15Z
dc.type.status.fl_str_mv info:eu-repo/semantics/publishedVersion
dc.type.driver.fl_str_mv info:eu-repo/semantics/masterThesis
format masterThesis
status_str publishedVersion
dc.identifier.citation.fl_str_mv OLIVEIRA, Erikson Ricardo Marques de. Metodologia de implantação da construção enxuta: estudo de caso em construtora de porte médio. 2013. 175 f. Dissertação (Mestrado em MECÂNICA DAS ESTRUTURAS, ESTRUTURAS DE CONCRETO E ALVENARIA E MATERIAIS E PROCESSOS CONSTRUTIVOS) - Universidade Federal do Rio Grande do Norte, Natal, 2013.
dc.identifier.uri.fl_str_mv https://repositorio.ufrn.br/jspui/handle/123456789/14848
identifier_str_mv OLIVEIRA, Erikson Ricardo Marques de. Metodologia de implantação da construção enxuta: estudo de caso em construtora de porte médio. 2013. 175 f. Dissertação (Mestrado em MECÂNICA DAS ESTRUTURAS, ESTRUTURAS DE CONCRETO E ALVENARIA E MATERIAIS E PROCESSOS CONSTRUTIVOS) - Universidade Federal do Rio Grande do Norte, Natal, 2013.
url https://repositorio.ufrn.br/jspui/handle/123456789/14848
dc.language.iso.fl_str_mv por
language por
dc.rights.driver.fl_str_mv info:eu-repo/semantics/openAccess
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv application/pdf
dc.publisher.none.fl_str_mv Universidade Federal do Rio Grande do Norte
dc.publisher.program.fl_str_mv Programa de Pós-Graduação em Engenharia Civil
dc.publisher.initials.fl_str_mv UFRN
dc.publisher.country.fl_str_mv BR
dc.publisher.department.fl_str_mv MECÂNICA DAS ESTRUTURAS, ESTRUTURAS DE CONCRETO E ALVENARIA E MATERIAIS E PROCESSOS CONSTRUTIVOS
publisher.none.fl_str_mv Universidade Federal do Rio Grande do Norte
dc.source.none.fl_str_mv reponame:Repositório Institucional da UFRN
instname:Universidade Federal do Rio Grande do Norte (UFRN)
instacron:UFRN
instname_str Universidade Federal do Rio Grande do Norte (UFRN)
instacron_str UFRN
institution UFRN
reponame_str Repositório Institucional da UFRN
collection Repositório Institucional da UFRN
bitstream.url.fl_str_mv https://repositorio.ufrn.br/bitstream/123456789/14848/1/EriksonRMO_DISSERT.pdf
https://repositorio.ufrn.br/bitstream/123456789/14848/6/EriksonRMO_DISSERT.pdf.txt
https://repositorio.ufrn.br/bitstream/123456789/14848/7/EriksonRMO_DISSERT.pdf.jpg
bitstream.checksum.fl_str_mv e7be854fab647e1f1602ce7096cdca4c
35831641c699f979e9f0d42db683f18c
a340f2298463864231f4954688396411
bitstream.checksumAlgorithm.fl_str_mv MD5
MD5
MD5
repository.name.fl_str_mv Repositório Institucional da UFRN - Universidade Federal do Rio Grande do Norte (UFRN)
repository.mail.fl_str_mv
_version_ 1814832788975648768