Resumo: Abstract: Good design and construction planning are essential to ensure the quality of the final product. To do this, it is necessary to develop an integrated organizational system for production and work schedule control, just in time material delivery, job site layout planning and real-time task management. The main objective of this work is to propose a method to improve process flow planning of prefabricated concrete panels based on the software application that uses Visilean® to monitor the movement of the parts in the factory. Visilean® model was useful for the visual verification of project, production and installation processes allowing suggestions for improvements to operational procedures. Research’s contribution is to propose a method for integrated planning that favors scenarios creation to anticipate possible problems that usually occur in both production flow and information flow. In practice, the researchers created a simple interface that allows operators to visualize times, production services and their sequence in real-time. Better visualization of the processes and control has a great impact on the final product’s quality, as well as, timely delivery and improved communication between project, production and construction teams. For future research, the inclusion of the Internet of Things for process automation will be an essential complement to the model.
id UFSCAR-3_0d4be3d8a8a3e999cd8d8d14a97f2912
oai_identifier_str oai:scielo:S0104-530X2021000300218
network_acronym_str UFSCAR-3
network_name_str Gestão & Produção
repository_id_str
spelling Visilean® application for monitoring and control of pre-fabricated concrete panelsPre-fabricated concreteLean constructionIndustrializationKanBIM™Visilean®Abstract: Good design and construction planning are essential to ensure the quality of the final product. To do this, it is necessary to develop an integrated organizational system for production and work schedule control, just in time material delivery, job site layout planning and real-time task management. The main objective of this work is to propose a method to improve process flow planning of prefabricated concrete panels based on the software application that uses Visilean® to monitor the movement of the parts in the factory. Visilean® model was useful for the visual verification of project, production and installation processes allowing suggestions for improvements to operational procedures. Research’s contribution is to propose a method for integrated planning that favors scenarios creation to anticipate possible problems that usually occur in both production flow and information flow. In practice, the researchers created a simple interface that allows operators to visualize times, production services and their sequence in real-time. Better visualization of the processes and control has a great impact on the final product’s quality, as well as, timely delivery and improved communication between project, production and construction teams. For future research, the inclusion of the Internet of Things for process automation will be an essential complement to the model.Universidade Federal de São Carlos2021-01-01info:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersiontext/htmlhttp://old.scielo.br/scielo.php?script=sci_arttext&pid=S0104-530X2021000300218Gestão & Produção v.28 n.3 2021reponame:Gestão & Produçãoinstname:Universidade Federal de São Carlos (UFSCAR)instacron:UFSCAR10.1590/1806-9649-2021v28e5800info:eu-repo/semantics/openAccessKanai,JuliaGomes,Carlos Eduardo MarmoratoBertoli,Stelamaris RollaFontanini,Patricia Stella Pucharellieng2021-07-29T00:00:00Zoai:scielo:S0104-530X2021000300218Revistahttps://www.gestaoeproducao.com/PUBhttps://old.scielo.br/oai/scielo-oai.phpgp@dep.ufscar.br||revistagestaoemanalise@unichristus.edu.br1806-96490104-530Xopendoar:2021-07-29T00:00Gestão & Produção - Universidade Federal de São Carlos (UFSCAR)false
dc.title.none.fl_str_mv Visilean® application for monitoring and control of pre-fabricated concrete panels
title Visilean® application for monitoring and control of pre-fabricated concrete panels
spellingShingle Visilean® application for monitoring and control of pre-fabricated concrete panels
Kanai,Julia
Pre-fabricated concrete
Lean construction
Industrialization
KanBIM™
Visilean®
title_short Visilean® application for monitoring and control of pre-fabricated concrete panels
title_full Visilean® application for monitoring and control of pre-fabricated concrete panels
title_fullStr Visilean® application for monitoring and control of pre-fabricated concrete panels
title_full_unstemmed Visilean® application for monitoring and control of pre-fabricated concrete panels
title_sort Visilean® application for monitoring and control of pre-fabricated concrete panels
author Kanai,Julia
author_facet Kanai,Julia
Gomes,Carlos Eduardo Marmorato
Bertoli,Stelamaris Rolla
Fontanini,Patricia Stella Pucharelli
author_role author
author2 Gomes,Carlos Eduardo Marmorato
Bertoli,Stelamaris Rolla
Fontanini,Patricia Stella Pucharelli
author2_role author
author
author
dc.contributor.author.fl_str_mv Kanai,Julia
Gomes,Carlos Eduardo Marmorato
Bertoli,Stelamaris Rolla
Fontanini,Patricia Stella Pucharelli
dc.subject.por.fl_str_mv Pre-fabricated concrete
Lean construction
Industrialization
KanBIM™
Visilean®
topic Pre-fabricated concrete
Lean construction
Industrialization
KanBIM™
Visilean®
description Abstract: Good design and construction planning are essential to ensure the quality of the final product. To do this, it is necessary to develop an integrated organizational system for production and work schedule control, just in time material delivery, job site layout planning and real-time task management. The main objective of this work is to propose a method to improve process flow planning of prefabricated concrete panels based on the software application that uses Visilean® to monitor the movement of the parts in the factory. Visilean® model was useful for the visual verification of project, production and installation processes allowing suggestions for improvements to operational procedures. Research’s contribution is to propose a method for integrated planning that favors scenarios creation to anticipate possible problems that usually occur in both production flow and information flow. In practice, the researchers created a simple interface that allows operators to visualize times, production services and their sequence in real-time. Better visualization of the processes and control has a great impact on the final product’s quality, as well as, timely delivery and improved communication between project, production and construction teams. For future research, the inclusion of the Internet of Things for process automation will be an essential complement to the model.
publishDate 2021
dc.date.none.fl_str_mv 2021-01-01
dc.type.driver.fl_str_mv info:eu-repo/semantics/article
dc.type.status.fl_str_mv info:eu-repo/semantics/publishedVersion
format article
status_str publishedVersion
dc.identifier.uri.fl_str_mv http://old.scielo.br/scielo.php?script=sci_arttext&pid=S0104-530X2021000300218
url http://old.scielo.br/scielo.php?script=sci_arttext&pid=S0104-530X2021000300218
dc.language.iso.fl_str_mv eng
language eng
dc.relation.none.fl_str_mv 10.1590/1806-9649-2021v28e5800
dc.rights.driver.fl_str_mv info:eu-repo/semantics/openAccess
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv text/html
dc.publisher.none.fl_str_mv Universidade Federal de São Carlos
publisher.none.fl_str_mv Universidade Federal de São Carlos
dc.source.none.fl_str_mv Gestão & Produção v.28 n.3 2021
reponame:Gestão & Produção
instname:Universidade Federal de São Carlos (UFSCAR)
instacron:UFSCAR
instname_str Universidade Federal de São Carlos (UFSCAR)
instacron_str UFSCAR
institution UFSCAR
reponame_str Gestão & Produção
collection Gestão & Produção
repository.name.fl_str_mv Gestão & Produção - Universidade Federal de São Carlos (UFSCAR)
repository.mail.fl_str_mv gp@dep.ufscar.br||revistagestaoemanalise@unichristus.edu.br
_version_ 1750118207962742784