EROSÃO MARGINAL: MUDANÇAS GEOMORFOLÓGICAS NO RIO TELES PIRES (MT) DECORRENTE DA IMPLANTAÇÃO DE UM BARRAMENTO
Autor(a) principal: | |
---|---|
Data de Publicação: | 2020 |
Outros Autores: | , , , , |
Tipo de documento: | Artigo |
Idioma: | por |
Título da fonte: | Caminhos de Geografia |
Texto Completo: | https://seer.ufu.br/index.php/caminhosdegeografia/article/view/51056 |
Resumo: | The objective of this research was to quantify the river bank erosion and identify the hydrological and geomorphological effects following the installation and operation of the Colider Hydroelectric Power Plant (HPP). We conducted a bibliographical survey; fieldwork, over a two-year period, for soil collection, instrumentation and monitoring of bank erosion; and deskwork to create sketches, calculate the magnitude of erosion, and conduct laboratory analyses. We verified that the river banks eroded slowly, beginning to precipitate the corrosion process. However, erosion was 12% greater in 2018 than to 2017. When correlating thel factors (velocity, flow, slope, ravine height and others) the Principal Component Analysis explained 63% of the variation observed. In the reservoir, the banks and several islands were submerged, damaging the habitat of various species. The transformations due to the installation of the Colider HPP imply an increase in the erosive process. |
id |
UFU-16_f0f6cc7e7031a676017e59b132dbb1c9 |
---|---|
oai_identifier_str |
oai:ojs.www.seer.ufu.br:article/51056 |
network_acronym_str |
UFU-16 |
network_name_str |
Caminhos de Geografia |
repository_id_str |
|
spelling |
EROSÃO MARGINAL: MUDANÇAS GEOMORFOLÓGICAS NO RIO TELES PIRES (MT) DECORRENTE DA IMPLANTAÇÃO DE UM BARRAMENTOProcessos erosivosUHE ColiderMudança na PaisagemBacia AmazônicaErosive ProcessesColider HPPLandscape changeAmazon BasinThe objective of this research was to quantify the river bank erosion and identify the hydrological and geomorphological effects following the installation and operation of the Colider Hydroelectric Power Plant (HPP). We conducted a bibliographical survey; fieldwork, over a two-year period, for soil collection, instrumentation and monitoring of bank erosion; and deskwork to create sketches, calculate the magnitude of erosion, and conduct laboratory analyses. We verified that the river banks eroded slowly, beginning to precipitate the corrosion process. However, erosion was 12% greater in 2018 than to 2017. When correlating thel factors (velocity, flow, slope, ravine height and others) the Principal Component Analysis explained 63% of the variation observed. In the reservoir, the banks and several islands were submerged, damaging the habitat of various species. The transformations due to the installation of the Colider HPP imply an increase in the erosive process.A pesquisa teve como objetivo quantificar a erosão marginal e identificar os efeitos hidrológicos e geomorfológicos com a instalação e funcionamento da Usina Hidrelétrica - UHE Colider. Foram realizados: levantamento bibliográfico; trabalho de campo no período de dois anos para coleta de solo, instrumentalização e monitoramento da erosão marginal; trabalho de gabinete com confecção de croquis, cálculo da magnitude da erosão e análise em laboratório. Averiguou-se que as margens erodiram lentamente, passando a incidir o processo de abrasão. No entanto, pode-se constatar que a erosão aumentou 12% em 2018 se comparada a 2017. Ao correlacionar os fatores (velocidade, vazão, inclinação, altura do barranco e outros) verificou-se que Análise do Componente Principal explicou 63% da variação observada. No reservatório as margens e várias ilhas foram submersas, prejudicando o habitat de várias espécies. Conforme as transformações ocorridas com a instalação da UHE Colider, se não forem tomadas medidas de contensão das erosões marginais, provavelmente ocorrerá aumento dos processos erosivos.EDUFU - Editora da Universidade Federal de Uberlândia2020-05-31info:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersionAvaliado pelos paresapplication/pdfhttps://seer.ufu.br/index.php/caminhosdegeografia/article/view/5105610.14393/RCG217551056Caminhos de Geografia; Vol. 21 No. 75 (2020): Junho; 154-171Caminhos de Geografia; Vol. 21 Núm. 75 (2020): Junho; 154-171Caminhos de Geografia; v. 21 n. 75 (2020): Junho; 154-1711678-6343reponame:Caminhos de Geografiainstname:Universidade Federal de Uberlândia (UFU)instacron:UFUporhttps://seer.ufu.br/index.php/caminhosdegeografia/article/view/51056/29013Copyright (c) 2020 Paiva da Silva Andrade, Marcela Bianchessi da Cunha Santino, Celia Alves de Souza, Fabio Leandro da Silva, Juberto Babilônia de Sousa, Cristiano Campos de Mirandainfo:eu-repo/semantics/openAccessNalis Paiva da Silva Andrade, LeilaBianchessi da Cunha Santino, Marcela Alves de Souza, Celia Leandro da Silva, Fabio Babilônia de Sousa, Juberto Campos de Miranda, Cristiano 2020-06-17T19:06:58Zoai:ojs.www.seer.ufu.br:article/51056Revistahttps://seer.ufu.br/index.php/caminhosdegeografia/indexPUBhttp://www.seer.ufu.br/index.php/caminhosdegeografia/oaiflaviasantosgeo@gmail.com1678-63431678-6343opendoar:2020-06-17T19:06:58Caminhos de Geografia - Universidade Federal de Uberlândia (UFU)false |
dc.title.none.fl_str_mv |
EROSÃO MARGINAL: MUDANÇAS GEOMORFOLÓGICAS NO RIO TELES PIRES (MT) DECORRENTE DA IMPLANTAÇÃO DE UM BARRAMENTO |
title |
EROSÃO MARGINAL: MUDANÇAS GEOMORFOLÓGICAS NO RIO TELES PIRES (MT) DECORRENTE DA IMPLANTAÇÃO DE UM BARRAMENTO |
spellingShingle |
EROSÃO MARGINAL: MUDANÇAS GEOMORFOLÓGICAS NO RIO TELES PIRES (MT) DECORRENTE DA IMPLANTAÇÃO DE UM BARRAMENTO Nalis Paiva da Silva Andrade, Leila Processos erosivos UHE Colider Mudança na Paisagem Bacia Amazônica Erosive Processes Colider HPP Landscape change Amazon Basin |
title_short |
EROSÃO MARGINAL: MUDANÇAS GEOMORFOLÓGICAS NO RIO TELES PIRES (MT) DECORRENTE DA IMPLANTAÇÃO DE UM BARRAMENTO |
title_full |
EROSÃO MARGINAL: MUDANÇAS GEOMORFOLÓGICAS NO RIO TELES PIRES (MT) DECORRENTE DA IMPLANTAÇÃO DE UM BARRAMENTO |
title_fullStr |
EROSÃO MARGINAL: MUDANÇAS GEOMORFOLÓGICAS NO RIO TELES PIRES (MT) DECORRENTE DA IMPLANTAÇÃO DE UM BARRAMENTO |
title_full_unstemmed |
EROSÃO MARGINAL: MUDANÇAS GEOMORFOLÓGICAS NO RIO TELES PIRES (MT) DECORRENTE DA IMPLANTAÇÃO DE UM BARRAMENTO |
title_sort |
EROSÃO MARGINAL: MUDANÇAS GEOMORFOLÓGICAS NO RIO TELES PIRES (MT) DECORRENTE DA IMPLANTAÇÃO DE UM BARRAMENTO |
author |
Nalis Paiva da Silva Andrade, Leila |
author_facet |
Nalis Paiva da Silva Andrade, Leila Bianchessi da Cunha Santino, Marcela Alves de Souza, Celia Leandro da Silva, Fabio Babilônia de Sousa, Juberto Campos de Miranda, Cristiano |
author_role |
author |
author2 |
Bianchessi da Cunha Santino, Marcela Alves de Souza, Celia Leandro da Silva, Fabio Babilônia de Sousa, Juberto Campos de Miranda, Cristiano |
author2_role |
author author author author author |
dc.contributor.author.fl_str_mv |
Nalis Paiva da Silva Andrade, Leila Bianchessi da Cunha Santino, Marcela Alves de Souza, Celia Leandro da Silva, Fabio Babilônia de Sousa, Juberto Campos de Miranda, Cristiano |
dc.subject.por.fl_str_mv |
Processos erosivos UHE Colider Mudança na Paisagem Bacia Amazônica Erosive Processes Colider HPP Landscape change Amazon Basin |
topic |
Processos erosivos UHE Colider Mudança na Paisagem Bacia Amazônica Erosive Processes Colider HPP Landscape change Amazon Basin |
description |
The objective of this research was to quantify the river bank erosion and identify the hydrological and geomorphological effects following the installation and operation of the Colider Hydroelectric Power Plant (HPP). We conducted a bibliographical survey; fieldwork, over a two-year period, for soil collection, instrumentation and monitoring of bank erosion; and deskwork to create sketches, calculate the magnitude of erosion, and conduct laboratory analyses. We verified that the river banks eroded slowly, beginning to precipitate the corrosion process. However, erosion was 12% greater in 2018 than to 2017. When correlating thel factors (velocity, flow, slope, ravine height and others) the Principal Component Analysis explained 63% of the variation observed. In the reservoir, the banks and several islands were submerged, damaging the habitat of various species. The transformations due to the installation of the Colider HPP imply an increase in the erosive process. |
publishDate |
2020 |
dc.date.none.fl_str_mv |
2020-05-31 |
dc.type.driver.fl_str_mv |
info:eu-repo/semantics/article info:eu-repo/semantics/publishedVersion Avaliado pelos pares |
format |
article |
status_str |
publishedVersion |
dc.identifier.uri.fl_str_mv |
https://seer.ufu.br/index.php/caminhosdegeografia/article/view/51056 10.14393/RCG217551056 |
url |
https://seer.ufu.br/index.php/caminhosdegeografia/article/view/51056 |
identifier_str_mv |
10.14393/RCG217551056 |
dc.language.iso.fl_str_mv |
por |
language |
por |
dc.relation.none.fl_str_mv |
https://seer.ufu.br/index.php/caminhosdegeografia/article/view/51056/29013 |
dc.rights.driver.fl_str_mv |
info:eu-repo/semantics/openAccess |
eu_rights_str_mv |
openAccess |
dc.format.none.fl_str_mv |
application/pdf |
dc.publisher.none.fl_str_mv |
EDUFU - Editora da Universidade Federal de Uberlândia |
publisher.none.fl_str_mv |
EDUFU - Editora da Universidade Federal de Uberlândia |
dc.source.none.fl_str_mv |
Caminhos de Geografia; Vol. 21 No. 75 (2020): Junho; 154-171 Caminhos de Geografia; Vol. 21 Núm. 75 (2020): Junho; 154-171 Caminhos de Geografia; v. 21 n. 75 (2020): Junho; 154-171 1678-6343 reponame:Caminhos de Geografia instname:Universidade Federal de Uberlândia (UFU) instacron:UFU |
instname_str |
Universidade Federal de Uberlândia (UFU) |
instacron_str |
UFU |
institution |
UFU |
reponame_str |
Caminhos de Geografia |
collection |
Caminhos de Geografia |
repository.name.fl_str_mv |
Caminhos de Geografia - Universidade Federal de Uberlândia (UFU) |
repository.mail.fl_str_mv |
flaviasantosgeo@gmail.com |
_version_ |
1797067017228910592 |