Causes of delays in the conclusion of public works: a comparative analysis by bibliometric research and case study

Detalhes bibliográficos
Autor(a) principal: Andrade D’Angelo, Aldo César
Data de Publicação: 2023
Outros Autores: Fernandes Gomes Guimarães, Irce, Magalhães do Vale, Clécio
Tipo de documento: Artigo
Idioma: por
Título da fonte: Revista Gestão e Projetos (GeP)
Texto Completo: https://periodicos.uninove.br/gep/article/view/22740
Resumo: and maintenance of the real estate. Given this, this study aimed to investigate the reasons for delays and additions in works contracted by Public Education Institutions. To investigate the main causes, a bibliographic review and a bibliometric study were carried out. Then, a case study was developed in a Higher Education Institution (IFES) to evaluate if the reasons for these additions are common to those identified in the bibliometric analysis. To this end, we analyzed thirty-five construction contracts, 83% of which had their deadlines extended. The main causes were: a lack of project compatibility; errors in quantity surveys and spreadsheets; unrealistic contract duration; and delay in finalizing prices for extra items. In the bibliometric analysis, it was observed that service additions due to spreadsheet errors appeared in 66% of the works analyzed; service additions due to project errors in 55% of the contracts; and project changes during the execution of the work that generated financial and deadline additions in 52% of the works. Thus, it can be observed that the main problems that generate additives detected in the bibliometry are similar to those detected in the case study. Through these results, we warn about the importance of training professionals and investing in means, such as the use of specialized project management software to minimize or eliminate the occurrence of these causes in public works.
id UNINOVE-4_efe77067b5cb290c0601d7675f5c68ad
oai_identifier_str oai:ojs.periodicos.uninove.br:article/22740
network_acronym_str UNINOVE-4
network_name_str Revista Gestão e Projetos (GeP)
repository_id_str
spelling Causes of delays in the conclusion of public works: a comparative analysis by bibliometric research and case studyCausas de atrasos na conclusão de obras públicas: uma análise comparativa por pesquisa bibliométrica e estudo de casoPublic worksDelaysPlanningControl.Obras públicasAtrasosPlanejamentoControleand maintenance of the real estate. Given this, this study aimed to investigate the reasons for delays and additions in works contracted by Public Education Institutions. To investigate the main causes, a bibliographic review and a bibliometric study were carried out. Then, a case study was developed in a Higher Education Institution (IFES) to evaluate if the reasons for these additions are common to those identified in the bibliometric analysis. To this end, we analyzed thirty-five construction contracts, 83% of which had their deadlines extended. The main causes were: a lack of project compatibility; errors in quantity surveys and spreadsheets; unrealistic contract duration; and delay in finalizing prices for extra items. In the bibliometric analysis, it was observed that service additions due to spreadsheet errors appeared in 66% of the works analyzed; service additions due to project errors in 55% of the contracts; and project changes during the execution of the work that generated financial and deadline additions in 52% of the works. Thus, it can be observed that the main problems that generate additives detected in the bibliometry are similar to those detected in the case study. Through these results, we warn about the importance of training professionals and investing in means, such as the use of specialized project management software to minimize or eliminate the occurrence of these causes in public works.Uma das grandes preocupações da Administração Pública é a necessidade de aprimorar seus métodos de alocação de recursos financeiros em obras e manutenções imobiliárias. Diante disto, este estudo teve como objetivo investigar os motivos de atrasos e aditamentos em obras contratadas por Instituições de Ensino Público, visando buscar, por meio de estudos, possibilidades para minimizar a utilização de aditivos na execução das obras. Para a investigação das principais causas foram realizados uma revisão de literatura e um estudo bibliométrico. Em seguida, foi desenvolvido um estudo de caso em uma Instituição Federal de Ensino Superior (IFES) para avaliar se os motivos desses aditamentos são comuns aos identificados na análise por bibliometria. Para tal fim, analisou-se trinta e cinco contratos de obras, dos quais 83% deles obtiveram acréscimo de prazo. As principais causas foram: falta de compatibilização dos projetos e erros nos levantamentos de quantitativos e planilhas. Na análise bibliométrica, observou-se que os acréscimos de serviços devido a erros de planilhas apareceram em 66% das obras analisadas; acréscimos de serviços devido à erros de projetos em 55% dos contratos; e alterações de projetos durante a execução da obra que geraram aditivos financeiros e aditivos de prazo em 52% das obras. Logo, observa-se que os principais problemas geradores de aditivos detectados nos dois métodos de pesquisa são semelhantes. Por meio destes resultados, alerta-se que é importante capacitar profissionais e investir em meios como uso de softwares especializados de gestão dos projetos que minimizem ou eliminem a ocorrência destas causas em obras públicas.Universidade Nove de Julho - Uninove2023-03-31info:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersionapplication/pdfhttps://periodicos.uninove.br/gep/article/view/2274010.5585/gep.v14i1.22740Revista de Gestão e Projetos; v. 14 n. 1 (2023): (jan./abr.); 190-2182236-0972reponame:Revista Gestão e Projetos (GeP)instname:Universidade Nove de Julho (UNINOVE)instacron:UNINOVEporhttps://periodicos.uninove.br/gep/article/view/22740/10104Copyright (c) 2023 Dos autoreshttps://creativecommons.org/licenses/by-nc-sa/4.0info:eu-repo/semantics/openAccessAndrade D’Angelo, Aldo CésarFernandes Gomes Guimarães, IrceMagalhães do Vale, Clécio2023-03-31T14:44:47Zoai:ojs.periodicos.uninove.br:article/22740Revistahttps://periodicos.uninove.br/gepPRIhttps://periodicos.uninove.br/gep/oaigep@uninove.br || editor@revistagep.org || crismonteiro@uninove.br2236-09722236-0972opendoar:2023-03-31T14:44:47Revista Gestão e Projetos (GeP) - Universidade Nove de Julho (UNINOVE)false
dc.title.none.fl_str_mv Causes of delays in the conclusion of public works: a comparative analysis by bibliometric research and case study
Causas de atrasos na conclusão de obras públicas: uma análise comparativa por pesquisa bibliométrica e estudo de caso
title Causes of delays in the conclusion of public works: a comparative analysis by bibliometric research and case study
spellingShingle Causes of delays in the conclusion of public works: a comparative analysis by bibliometric research and case study
Andrade D’Angelo, Aldo César
Public works
Delays
Planning
Control.
Obras públicas
Atrasos
Planejamento
Controle
title_short Causes of delays in the conclusion of public works: a comparative analysis by bibliometric research and case study
title_full Causes of delays in the conclusion of public works: a comparative analysis by bibliometric research and case study
title_fullStr Causes of delays in the conclusion of public works: a comparative analysis by bibliometric research and case study
title_full_unstemmed Causes of delays in the conclusion of public works: a comparative analysis by bibliometric research and case study
title_sort Causes of delays in the conclusion of public works: a comparative analysis by bibliometric research and case study
author Andrade D’Angelo, Aldo César
author_facet Andrade D’Angelo, Aldo César
Fernandes Gomes Guimarães, Irce
Magalhães do Vale, Clécio
author_role author
author2 Fernandes Gomes Guimarães, Irce
Magalhães do Vale, Clécio
author2_role author
author
dc.contributor.author.fl_str_mv Andrade D’Angelo, Aldo César
Fernandes Gomes Guimarães, Irce
Magalhães do Vale, Clécio
dc.subject.por.fl_str_mv Public works
Delays
Planning
Control.
Obras públicas
Atrasos
Planejamento
Controle
topic Public works
Delays
Planning
Control.
Obras públicas
Atrasos
Planejamento
Controle
description and maintenance of the real estate. Given this, this study aimed to investigate the reasons for delays and additions in works contracted by Public Education Institutions. To investigate the main causes, a bibliographic review and a bibliometric study were carried out. Then, a case study was developed in a Higher Education Institution (IFES) to evaluate if the reasons for these additions are common to those identified in the bibliometric analysis. To this end, we analyzed thirty-five construction contracts, 83% of which had their deadlines extended. The main causes were: a lack of project compatibility; errors in quantity surveys and spreadsheets; unrealistic contract duration; and delay in finalizing prices for extra items. In the bibliometric analysis, it was observed that service additions due to spreadsheet errors appeared in 66% of the works analyzed; service additions due to project errors in 55% of the contracts; and project changes during the execution of the work that generated financial and deadline additions in 52% of the works. Thus, it can be observed that the main problems that generate additives detected in the bibliometry are similar to those detected in the case study. Through these results, we warn about the importance of training professionals and investing in means, such as the use of specialized project management software to minimize or eliminate the occurrence of these causes in public works.
publishDate 2023
dc.date.none.fl_str_mv 2023-03-31
dc.type.driver.fl_str_mv info:eu-repo/semantics/article
info:eu-repo/semantics/publishedVersion
format article
status_str publishedVersion
dc.identifier.uri.fl_str_mv https://periodicos.uninove.br/gep/article/view/22740
10.5585/gep.v14i1.22740
url https://periodicos.uninove.br/gep/article/view/22740
identifier_str_mv 10.5585/gep.v14i1.22740
dc.language.iso.fl_str_mv por
language por
dc.relation.none.fl_str_mv https://periodicos.uninove.br/gep/article/view/22740/10104
dc.rights.driver.fl_str_mv Copyright (c) 2023 Dos autores
https://creativecommons.org/licenses/by-nc-sa/4.0
info:eu-repo/semantics/openAccess
rights_invalid_str_mv Copyright (c) 2023 Dos autores
https://creativecommons.org/licenses/by-nc-sa/4.0
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv application/pdf
dc.publisher.none.fl_str_mv Universidade Nove de Julho - Uninove
publisher.none.fl_str_mv Universidade Nove de Julho - Uninove
dc.source.none.fl_str_mv Revista de Gestão e Projetos; v. 14 n. 1 (2023): (jan./abr.); 190-218
2236-0972
reponame:Revista Gestão e Projetos (GeP)
instname:Universidade Nove de Julho (UNINOVE)
instacron:UNINOVE
instname_str Universidade Nove de Julho (UNINOVE)
instacron_str UNINOVE
institution UNINOVE
reponame_str Revista Gestão e Projetos (GeP)
collection Revista Gestão e Projetos (GeP)
repository.name.fl_str_mv Revista Gestão e Projetos (GeP) - Universidade Nove de Julho (UNINOVE)
repository.mail.fl_str_mv gep@uninove.br || editor@revistagep.org || crismonteiro@uninove.br
_version_ 1797052864570327040