Resumo: This project was carried out at a company in the electric mobility sector, which manufactures chargers for electric vehicles, specifically in the wiring section. The main objective of the developed work was to improve the production processes in order to enhance responsiveness to the growing demand. After analyzing the processes in the section, the objectives were outlined to enable the improvement of some practices in the production department, such as the ones related to the organization of the raw material supermarket, as well as the calculation of the wiring consumption by chargers, and the implementation of a production control system. After the improvement actions were implemented, it was possible to observe a 14,9% reduction in the changeover process of the cable cutting process; weekly wiring consumptions were estimated, and procedures were defined to generate orders of raw material and supply to the workstation, which led to the elimination of stock shortages. In addition, worker autonomy increased and production downtime was reduced.
id RCAP_79c190abee963f5856ac0efb60e52e48
oai_identifier_str oai:repositorio.ipcb.pt:10400.11/7305
network_acronym_str RCAP
network_name_str Repositório Científico de Acesso Aberto de Portugal (Repositórios Cientìficos)
repository_id_str 7160
spelling Lean manufacturing applied to a wiring production processLean manufacturingProcess improvements5SProduction controlChangeoverStock shortagesProduction practicesTime wastedThis project was carried out at a company in the electric mobility sector, which manufactures chargers for electric vehicles, specifically in the wiring section. The main objective of the developed work was to improve the production processes in order to enhance responsiveness to the growing demand. After analyzing the processes in the section, the objectives were outlined to enable the improvement of some practices in the production department, such as the ones related to the organization of the raw material supermarket, as well as the calculation of the wiring consumption by chargers, and the implementation of a production control system. After the improvement actions were implemented, it was possible to observe a 14,9% reduction in the changeover process of the cable cutting process; weekly wiring consumptions were estimated, and procedures were defined to generate orders of raw material and supply to the workstation, which led to the elimination of stock shortages. In addition, worker autonomy increased and production downtime was reduced.ElsevierRepositório Científico do Instituto Politécnico de Castelo BrancoPena, R.Ferreira, L.P.Silva, F.J.G.Sá, J.C.Fernandes, N.O.G.Pereira, T.2020-11-23T10:37:51Z2020-112020-11-01T00:00:00Zinfo:eu-repo/semantics/publishedVersioninfo:eu-repo/semantics/articleapplication/pdfhttp://hdl.handle.net/10400.11/7305engPENA, R. [et al.] (2020) - Lean manufacturing applied to a wiring production process. Procedia Manufacturing. ISSN 2351-9789. [S.l.] : Elsevier, 51. p. 1387–1394. DOI: 10.1016/j.promfg.2020.10.1932351-978910.1016/j.promfg.2020.10.193info:eu-repo/semantics/openAccessreponame:Repositório Científico de Acesso Aberto de Portugal (Repositórios Cientìficos)instname:Agência para a Sociedade do Conhecimento (UMIC) - FCT - Sociedade da Informaçãoinstacron:RCAAP2023-01-16T11:47:47Zoai:repositorio.ipcb.pt:10400.11/7305Portal AgregadorONGhttps://www.rcaap.pt/oai/openaireopendoar:71602024-03-19T16:37:52.298208Repositório Científico de Acesso Aberto de Portugal (Repositórios Cientìficos) - Agência para a Sociedade do Conhecimento (UMIC) - FCT - Sociedade da Informaçãofalse
dc.title.none.fl_str_mv Lean manufacturing applied to a wiring production process
title Lean manufacturing applied to a wiring production process
spellingShingle Lean manufacturing applied to a wiring production process
Pena, R.
Lean manufacturing
Process improvements
5S
Production control
Changeover
Stock shortages
Production practices
Time wasted
title_short Lean manufacturing applied to a wiring production process
title_full Lean manufacturing applied to a wiring production process
title_fullStr Lean manufacturing applied to a wiring production process
title_full_unstemmed Lean manufacturing applied to a wiring production process
title_sort Lean manufacturing applied to a wiring production process
author Pena, R.
author_facet Pena, R.
Ferreira, L.P.
Silva, F.J.G.
Sá, J.C.
Fernandes, N.O.G.
Pereira, T.
author_role author
author2 Ferreira, L.P.
Silva, F.J.G.
Sá, J.C.
Fernandes, N.O.G.
Pereira, T.
author2_role author
author
author
author
author
dc.contributor.none.fl_str_mv Repositório Científico do Instituto Politécnico de Castelo Branco
dc.contributor.author.fl_str_mv Pena, R.
Ferreira, L.P.
Silva, F.J.G.
Sá, J.C.
Fernandes, N.O.G.
Pereira, T.
dc.subject.por.fl_str_mv Lean manufacturing
Process improvements
5S
Production control
Changeover
Stock shortages
Production practices
Time wasted
topic Lean manufacturing
Process improvements
5S
Production control
Changeover
Stock shortages
Production practices
Time wasted
description This project was carried out at a company in the electric mobility sector, which manufactures chargers for electric vehicles, specifically in the wiring section. The main objective of the developed work was to improve the production processes in order to enhance responsiveness to the growing demand. After analyzing the processes in the section, the objectives were outlined to enable the improvement of some practices in the production department, such as the ones related to the organization of the raw material supermarket, as well as the calculation of the wiring consumption by chargers, and the implementation of a production control system. After the improvement actions were implemented, it was possible to observe a 14,9% reduction in the changeover process of the cable cutting process; weekly wiring consumptions were estimated, and procedures were defined to generate orders of raw material and supply to the workstation, which led to the elimination of stock shortages. In addition, worker autonomy increased and production downtime was reduced.
publishDate 2020
dc.date.none.fl_str_mv 2020-11-23T10:37:51Z
2020-11
2020-11-01T00:00:00Z
dc.type.status.fl_str_mv info:eu-repo/semantics/publishedVersion
dc.type.driver.fl_str_mv info:eu-repo/semantics/article
format article
status_str publishedVersion
dc.identifier.uri.fl_str_mv http://hdl.handle.net/10400.11/7305
url http://hdl.handle.net/10400.11/7305
dc.language.iso.fl_str_mv eng
language eng
dc.relation.none.fl_str_mv PENA, R. [et al.] (2020) - Lean manufacturing applied to a wiring production process. Procedia Manufacturing. ISSN 2351-9789. [S.l.] : Elsevier, 51. p. 1387–1394. DOI: 10.1016/j.promfg.2020.10.193
2351-9789
10.1016/j.promfg.2020.10.193
dc.rights.driver.fl_str_mv info:eu-repo/semantics/openAccess
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv application/pdf
dc.publisher.none.fl_str_mv Elsevier
publisher.none.fl_str_mv Elsevier
dc.source.none.fl_str_mv reponame:Repositório Científico de Acesso Aberto de Portugal (Repositórios Cientìficos)
instname:Agência para a Sociedade do Conhecimento (UMIC) - FCT - Sociedade da Informação
instacron:RCAAP
instname_str Agência para a Sociedade do Conhecimento (UMIC) - FCT - Sociedade da Informação
instacron_str RCAAP
institution RCAAP
reponame_str Repositório Científico de Acesso Aberto de Portugal (Repositórios Cientìficos)
collection Repositório Científico de Acesso Aberto de Portugal (Repositórios Cientìficos)
repository.name.fl_str_mv Repositório Científico de Acesso Aberto de Portugal (Repositórios Cientìficos) - Agência para a Sociedade do Conhecimento (UMIC) - FCT - Sociedade da Informação
repository.mail.fl_str_mv
_version_ 1799130841831440384