Mapping the value stream of the assembly process of a Horizontal Wet Christmas Tree in an offshore company

Detalhes bibliográficos
Autor(a) principal: Benini, Lucas
Data de Publicação: 2022
Outros Autores: Canellas, Luiza Garcia da Cruz, Achtschin, Paola de Freitas Borrelli, Moraes Júnior, José Mauro
Tipo de documento: Artigo
Idioma: por
Título da fonte: The Journal of Engineering and Exact Sciences
Texto Completo: https://periodicos.ufv.br/jcec/article/view/14342
Resumo: One of the main products used by offshore companies is the wet Christmas tree (XT), responsible for controlling the flow of fluids produced or injected into wells. The assembly of the components of a XT has a high degree of difficulty, especially in some stages, which ends up significantly increasing the pre-established lead time, raising the waste in the assembly. This waste led to interruptions in the production line and resources beyond necessary are dedicated to the resolution of these non-conformities. The goal of this work is to apply lean manufacturing tools on the assembly line of the horizontal wet Christmas tree and to propose solutions to eliminate all the identified waste. To do so, the project traced the following developments: (i) the current state of the process of assembling the XT was mapped; (ii) waste was identified; (iii) improvements were proposed through the application of lean tools and (iv) the map of the future state was prepared. Therefore, it was possible to conclude that through the mapping of the value flow aligned with the implementations of other lean tools, a reduction of approximately 26% of the lead time of the wet Christmas tree e assembly is possible to be achieved.
id UFV-6_f373ccb231bfb5863896f96a1d698aba
oai_identifier_str oai:ojs.periodicos.ufv.br:article/14342
network_acronym_str UFV-6
network_name_str The Journal of Engineering and Exact Sciences
repository_id_str
spelling Mapping the value stream of the assembly process of a Horizontal Wet Christmas Tree in an offshore companyMapeamento do fluxo de valor do processo de montagem de uma Árvore de Natal Molhada Horizontal em uma empresa do segmento offshore Lean manufacturingOffshoreÁrvore de natal molhadaMapa de fluxo de valorLinha de montagemLean manufacturing. Offshore. Christmas tree. Assembly line. Value stream mapping. One of the main products used by offshore companies is the wet Christmas tree (XT), responsible for controlling the flow of fluids produced or injected into wells. The assembly of the components of a XT has a high degree of difficulty, especially in some stages, which ends up significantly increasing the pre-established lead time, raising the waste in the assembly. This waste led to interruptions in the production line and resources beyond necessary are dedicated to the resolution of these non-conformities. The goal of this work is to apply lean manufacturing tools on the assembly line of the horizontal wet Christmas tree and to propose solutions to eliminate all the identified waste. To do so, the project traced the following developments: (i) the current state of the process of assembling the XT was mapped; (ii) waste was identified; (iii) improvements were proposed through the application of lean tools and (iv) the map of the future state was prepared. Therefore, it was possible to conclude that through the mapping of the value flow aligned with the implementations of other lean tools, a reduction of approximately 26% of the lead time of the wet Christmas tree e assembly is possible to be achieved.Um dos principais produtos utilizados por empresas offshore é a árvore de natal molhada (ANM) responsável por controlar o fluxo dos fluidos produzidos ou injetados em poços de petróleo. A montagem dos componentes de uma ANM possui um alto grau de dificuldade, principalmente em algumas etapas, que acabam aumentado significativamente os tempos de montagem (lead time) pré-estabelecidos, aumentando os desperdícios na produção. Estes desperdícios repercutem em interrupções na linha de montagem e recursos além do necessário são dedicados à resolução dessas não conformidades. O objetivo do trabalho é aplicar ferramentas do lean manufacturing na linha de montagem de uma de árvore de natal molhada do tipo horizontal e propor soluções para eliminar os desperdícios identificados. Para isto, o projeto seguiu o seguinte desdobramento: (i) mapeou-se o estado atual do processo de montagem da árvore de natal; (ii) identificou-se os desperdícios; (iii) foram propostas melhorias por meio de aplicação de ferramentas lean e (iv) elaborou-se o mapa do estado futuro. Com isto, foi possível concluir que através do mapeamento do fluxo de valor, em conjunto com as implementações de outras ferramentas lean, a redução de cerca de 26% do lead time da montagem da árvore de natal molhada é possível de ser atingida.Universidade Federal de Viçosa - UFV2022-06-09info:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersionArtigo, Manuscrito, Eventosapplication/pdfhttps://periodicos.ufv.br/jcec/article/view/1434210.18540/jcecvl8iss3pp14342-01iThe Journal of Engineering and Exact Sciences; Vol. 8 No. 3 (2022); 14342-01iThe Journal of Engineering and Exact Sciences; Vol. 8 Núm. 3 (2022); 14342-01iThe Journal of Engineering and Exact Sciences; v. 8 n. 3 (2022); 14342-01i2527-1075reponame:The Journal of Engineering and Exact Sciencesinstname:Universidade Federal de Viçosa (UFV)instacron:UFVporhttps://periodicos.ufv.br/jcec/article/view/14342/7356Copyright (c) 2022 The Journal of Engineering and Exact Scienceshttps://creativecommons.org/licenses/by/4.0info:eu-repo/semantics/openAccessBenini, LucasCanellas, Luiza Garcia da CruzAchtschin, Paola de Freitas BorrelliMoraes Júnior, José Mauro2022-06-29T13:37:54Zoai:ojs.periodicos.ufv.br:article/14342Revistahttp://www.seer.ufv.br/seer/rbeq2/index.php/req2/oai2527-10752527-1075opendoar:2022-06-29T13:37:54The Journal of Engineering and Exact Sciences - Universidade Federal de Viçosa (UFV)false
dc.title.none.fl_str_mv Mapping the value stream of the assembly process of a Horizontal Wet Christmas Tree in an offshore company
Mapeamento do fluxo de valor do processo de montagem de uma Árvore de Natal Molhada Horizontal em uma empresa do segmento offshore
title Mapping the value stream of the assembly process of a Horizontal Wet Christmas Tree in an offshore company
spellingShingle Mapping the value stream of the assembly process of a Horizontal Wet Christmas Tree in an offshore company
Benini, Lucas
Lean manufacturing
Offshore
Árvore de natal molhada
Mapa de fluxo de valor
Linha de montagem
Lean manufacturing. Offshore. Christmas tree. Assembly line. Value stream mapping.
title_short Mapping the value stream of the assembly process of a Horizontal Wet Christmas Tree in an offshore company
title_full Mapping the value stream of the assembly process of a Horizontal Wet Christmas Tree in an offshore company
title_fullStr Mapping the value stream of the assembly process of a Horizontal Wet Christmas Tree in an offshore company
title_full_unstemmed Mapping the value stream of the assembly process of a Horizontal Wet Christmas Tree in an offshore company
title_sort Mapping the value stream of the assembly process of a Horizontal Wet Christmas Tree in an offshore company
author Benini, Lucas
author_facet Benini, Lucas
Canellas, Luiza Garcia da Cruz
Achtschin, Paola de Freitas Borrelli
Moraes Júnior, José Mauro
author_role author
author2 Canellas, Luiza Garcia da Cruz
Achtschin, Paola de Freitas Borrelli
Moraes Júnior, José Mauro
author2_role author
author
author
dc.contributor.author.fl_str_mv Benini, Lucas
Canellas, Luiza Garcia da Cruz
Achtschin, Paola de Freitas Borrelli
Moraes Júnior, José Mauro
dc.subject.por.fl_str_mv Lean manufacturing
Offshore
Árvore de natal molhada
Mapa de fluxo de valor
Linha de montagem
Lean manufacturing. Offshore. Christmas tree. Assembly line. Value stream mapping.
topic Lean manufacturing
Offshore
Árvore de natal molhada
Mapa de fluxo de valor
Linha de montagem
Lean manufacturing. Offshore. Christmas tree. Assembly line. Value stream mapping.
description One of the main products used by offshore companies is the wet Christmas tree (XT), responsible for controlling the flow of fluids produced or injected into wells. The assembly of the components of a XT has a high degree of difficulty, especially in some stages, which ends up significantly increasing the pre-established lead time, raising the waste in the assembly. This waste led to interruptions in the production line and resources beyond necessary are dedicated to the resolution of these non-conformities. The goal of this work is to apply lean manufacturing tools on the assembly line of the horizontal wet Christmas tree and to propose solutions to eliminate all the identified waste. To do so, the project traced the following developments: (i) the current state of the process of assembling the XT was mapped; (ii) waste was identified; (iii) improvements were proposed through the application of lean tools and (iv) the map of the future state was prepared. Therefore, it was possible to conclude that through the mapping of the value flow aligned with the implementations of other lean tools, a reduction of approximately 26% of the lead time of the wet Christmas tree e assembly is possible to be achieved.
publishDate 2022
dc.date.none.fl_str_mv 2022-06-09
dc.type.driver.fl_str_mv info:eu-repo/semantics/article
info:eu-repo/semantics/publishedVersion
Artigo, Manuscrito, Eventos
format article
status_str publishedVersion
dc.identifier.uri.fl_str_mv https://periodicos.ufv.br/jcec/article/view/14342
10.18540/jcecvl8iss3pp14342-01i
url https://periodicos.ufv.br/jcec/article/view/14342
identifier_str_mv 10.18540/jcecvl8iss3pp14342-01i
dc.language.iso.fl_str_mv por
language por
dc.relation.none.fl_str_mv https://periodicos.ufv.br/jcec/article/view/14342/7356
dc.rights.driver.fl_str_mv Copyright (c) 2022 The Journal of Engineering and Exact Sciences
https://creativecommons.org/licenses/by/4.0
info:eu-repo/semantics/openAccess
rights_invalid_str_mv Copyright (c) 2022 The Journal of Engineering and Exact Sciences
https://creativecommons.org/licenses/by/4.0
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv application/pdf
dc.publisher.none.fl_str_mv Universidade Federal de Viçosa - UFV
publisher.none.fl_str_mv Universidade Federal de Viçosa - UFV
dc.source.none.fl_str_mv The Journal of Engineering and Exact Sciences; Vol. 8 No. 3 (2022); 14342-01i
The Journal of Engineering and Exact Sciences; Vol. 8 Núm. 3 (2022); 14342-01i
The Journal of Engineering and Exact Sciences; v. 8 n. 3 (2022); 14342-01i
2527-1075
reponame:The Journal of Engineering and Exact Sciences
instname:Universidade Federal de Viçosa (UFV)
instacron:UFV
instname_str Universidade Federal de Viçosa (UFV)
instacron_str UFV
institution UFV
reponame_str The Journal of Engineering and Exact Sciences
collection The Journal of Engineering and Exact Sciences
repository.name.fl_str_mv The Journal of Engineering and Exact Sciences - Universidade Federal de Viçosa (UFV)
repository.mail.fl_str_mv
_version_ 1798313322080108544