Monte Carlo simulation applied to 5-year recertification projects in surface equipment for drilling offshore oil wells

Detalhes bibliográficos
Autor(a) principal: Freitas Rodrigues, Diogo
Data de Publicação: 2023
Outros Autores: Barbosa Sobral, Ana Paula
Tipo de documento: Artigo
Idioma: por
Título da fonte: Revista Gestão e Projetos (GeP)
Texto Completo: https://periodicos.uninove.br/gep/article/view/23452
Resumo: Several project management tools may be applied in oil and gas industry. The PERT tool, also known as estimate of three points, uses specialists’ info to calculate the duration of project schedule tasks, taking into consideration optimistic, most likely, and pessimistic scenarios, all of them related to project’s risks and uncertainty. Monte Carlo Simulation tool proposes a random numbers sampling process, applied throughout project critical path, to predict finishing probabilities within specific dates. This article aims to employ the Monte Carlo simulation as a tool for schedule management, based on risk analysis, applied to five-year recertification projects in surface equipment for drilling offshore oil wells. Therefore, using a combination of PERT and Monte Carlo Simulation tools, combine to other project management concepts, it was possible to perform a probability analysis and obtain a prediction of the project finish scenario, based on its risks and uncertainty analyzed. The results have shown the project original schedule had low chances of finishing within time stablished and so, the simulation performed contributes for the initial schedule revision and improvement.
id UNINOVE-4_a5e2402af1829ebb5bb1dae8b19cd254
oai_identifier_str oai:ojs.periodicos.uninove.br:article/23452
network_acronym_str UNINOVE-4
network_name_str Revista Gestão e Projetos (GeP)
repository_id_str
spelling Monte Carlo simulation applied to 5-year recertification projects in surface equipment for drilling offshore oil wellsSimulação de Monte Carlo aplicada à projetos de recertificação de 5 anos em equipamentos de superfície para perfuração de poços de petróleo offshoreOil and gasDrillingProject managementRisksScheduleCritical pathPERTSimulationMonte CarloPetróleo e gásPerfuraçãoGerenciamentos de projetosRiscosCronogramaCaminho críticoPERTSimulaçãoMonte CarloSeveral project management tools may be applied in oil and gas industry. The PERT tool, also known as estimate of three points, uses specialists’ info to calculate the duration of project schedule tasks, taking into consideration optimistic, most likely, and pessimistic scenarios, all of them related to project’s risks and uncertainty. Monte Carlo Simulation tool proposes a random numbers sampling process, applied throughout project critical path, to predict finishing probabilities within specific dates. This article aims to employ the Monte Carlo simulation as a tool for schedule management, based on risk analysis, applied to five-year recertification projects in surface equipment for drilling offshore oil wells. Therefore, using a combination of PERT and Monte Carlo Simulation tools, combine to other project management concepts, it was possible to perform a probability analysis and obtain a prediction of the project finish scenario, based on its risks and uncertainty analyzed. The results have shown the project original schedule had low chances of finishing within time stablished and so, the simulation performed contributes for the initial schedule revision and improvement.Diversas ferramentas do gerenciamento de projetos podem ser aplicadas nos serviços da indústria de petróleo e gás. A ferramenta PERT, também conhecida como estimativa de três pontos, utiliza-se da informação de especialistas para calcular a duração das atividades do cronograma do projeto, levando em consideração cenários otimistas, mais prováveis e pessimistas, todos relacionados às incertezas e riscos do projeto. A ferramenta da Simulação de Monte Carlo propõe um processo de amostragem de números aleatórios, aplicados ao longo do caminho crítico de um projeto, para prever as probabilidades de conclusão em datas específicas. Com base neste contexto, o objetivo desta pesquisa é empregar a simulação de Monte Carlo como uma ferramenta para o Gerenciamento de Cronograma a partir da análise dos riscos, aplicada à projetos de recertificação de cinco anos em equipamentos de superfície para perfuração de poços de petróleo offshore. Para tanto, foi utilizada a combinação das ferramentas PERT e Simulação de Monte Carlo, dentre outros conceitos de gerenciamento de projetos, o que possibilitou realizar uma análise de probabilidade e obter uma previsão do cenário de conclusão do projeto, baseado em suas incertezas e riscos analisados. Os resultados demostraram que o cronograma original do projeto possuía chances baixas de ser concluído dentro do prazo, de modo que a simulação realizada contribui para revisão e melhoria do cronograma inicial.Universidade Nove de Julho - Uninove2023-03-31info:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersionapplication/pdfhttps://periodicos.uninove.br/gep/article/view/2345210.5585/gep.v14i1.23452Revista de Gestão e Projetos; v. 14 n. 1 (2023): (jan./abr.); 96-1322236-0972reponame:Revista Gestão e Projetos (GeP)instname:Universidade Nove de Julho (UNINOVE)instacron:UNINOVEporhttps://periodicos.uninove.br/gep/article/view/23452/10101Copyright (c) 2023 Dos autoreshttps://creativecommons.org/licenses/by-nc-sa/4.0info:eu-repo/semantics/openAccessFreitas Rodrigues, DiogoBarbosa Sobral, Ana Paula2023-03-31T14:44:47Zoai:ojs.periodicos.uninove.br:article/23452Revistahttps://periodicos.uninove.br/gepPRIhttps://periodicos.uninove.br/gep/oaigep@uninove.br || editor@revistagep.org || crismonteiro@uninove.br2236-09722236-0972opendoar:2023-03-31T14:44:47Revista Gestão e Projetos (GeP) - Universidade Nove de Julho (UNINOVE)false
dc.title.none.fl_str_mv Monte Carlo simulation applied to 5-year recertification projects in surface equipment for drilling offshore oil wells
Simulação de Monte Carlo aplicada à projetos de recertificação de 5 anos em equipamentos de superfície para perfuração de poços de petróleo offshore
title Monte Carlo simulation applied to 5-year recertification projects in surface equipment for drilling offshore oil wells
spellingShingle Monte Carlo simulation applied to 5-year recertification projects in surface equipment for drilling offshore oil wells
Freitas Rodrigues, Diogo
Oil and gas
Drilling
Project management
Risks
Schedule
Critical path
PERT
Simulation
Monte Carlo
Petróleo e gás
Perfuração
Gerenciamentos de projetos
Riscos
Cronograma
Caminho crítico
PERT
Simulação
Monte Carlo
title_short Monte Carlo simulation applied to 5-year recertification projects in surface equipment for drilling offshore oil wells
title_full Monte Carlo simulation applied to 5-year recertification projects in surface equipment for drilling offshore oil wells
title_fullStr Monte Carlo simulation applied to 5-year recertification projects in surface equipment for drilling offshore oil wells
title_full_unstemmed Monte Carlo simulation applied to 5-year recertification projects in surface equipment for drilling offshore oil wells
title_sort Monte Carlo simulation applied to 5-year recertification projects in surface equipment for drilling offshore oil wells
author Freitas Rodrigues, Diogo
author_facet Freitas Rodrigues, Diogo
Barbosa Sobral, Ana Paula
author_role author
author2 Barbosa Sobral, Ana Paula
author2_role author
dc.contributor.author.fl_str_mv Freitas Rodrigues, Diogo
Barbosa Sobral, Ana Paula
dc.subject.por.fl_str_mv Oil and gas
Drilling
Project management
Risks
Schedule
Critical path
PERT
Simulation
Monte Carlo
Petróleo e gás
Perfuração
Gerenciamentos de projetos
Riscos
Cronograma
Caminho crítico
PERT
Simulação
Monte Carlo
topic Oil and gas
Drilling
Project management
Risks
Schedule
Critical path
PERT
Simulation
Monte Carlo
Petróleo e gás
Perfuração
Gerenciamentos de projetos
Riscos
Cronograma
Caminho crítico
PERT
Simulação
Monte Carlo
description Several project management tools may be applied in oil and gas industry. The PERT tool, also known as estimate of three points, uses specialists’ info to calculate the duration of project schedule tasks, taking into consideration optimistic, most likely, and pessimistic scenarios, all of them related to project’s risks and uncertainty. Monte Carlo Simulation tool proposes a random numbers sampling process, applied throughout project critical path, to predict finishing probabilities within specific dates. This article aims to employ the Monte Carlo simulation as a tool for schedule management, based on risk analysis, applied to five-year recertification projects in surface equipment for drilling offshore oil wells. Therefore, using a combination of PERT and Monte Carlo Simulation tools, combine to other project management concepts, it was possible to perform a probability analysis and obtain a prediction of the project finish scenario, based on its risks and uncertainty analyzed. The results have shown the project original schedule had low chances of finishing within time stablished and so, the simulation performed contributes for the initial schedule revision and improvement.
publishDate 2023
dc.date.none.fl_str_mv 2023-03-31
dc.type.driver.fl_str_mv info:eu-repo/semantics/article
info:eu-repo/semantics/publishedVersion
format article
status_str publishedVersion
dc.identifier.uri.fl_str_mv https://periodicos.uninove.br/gep/article/view/23452
10.5585/gep.v14i1.23452
url https://periodicos.uninove.br/gep/article/view/23452
identifier_str_mv 10.5585/gep.v14i1.23452
dc.language.iso.fl_str_mv por
language por
dc.relation.none.fl_str_mv https://periodicos.uninove.br/gep/article/view/23452/10101
dc.rights.driver.fl_str_mv Copyright (c) 2023 Dos autores
https://creativecommons.org/licenses/by-nc-sa/4.0
info:eu-repo/semantics/openAccess
rights_invalid_str_mv Copyright (c) 2023 Dos autores
https://creativecommons.org/licenses/by-nc-sa/4.0
eu_rights_str_mv openAccess
dc.format.none.fl_str_mv application/pdf
dc.publisher.none.fl_str_mv Universidade Nove de Julho - Uninove
publisher.none.fl_str_mv Universidade Nove de Julho - Uninove
dc.source.none.fl_str_mv Revista de Gestão e Projetos; v. 14 n. 1 (2023): (jan./abr.); 96-132
2236-0972
reponame:Revista Gestão e Projetos (GeP)
instname:Universidade Nove de Julho (UNINOVE)
instacron:UNINOVE
instname_str Universidade Nove de Julho (UNINOVE)
instacron_str UNINOVE
institution UNINOVE
reponame_str Revista Gestão e Projetos (GeP)
collection Revista Gestão e Projetos (GeP)
repository.name.fl_str_mv Revista Gestão e Projetos (GeP) - Universidade Nove de Julho (UNINOVE)
repository.mail.fl_str_mv gep@uninove.br || editor@revistagep.org || crismonteiro@uninove.br
_version_ 1797052864580812800